April 16, 2007
Site Remediation
Ten years to clean up Sydney Tar Ponds
SYDNEY TAR PONDS AGENCY
Over the winter, drilling was carried out as part of a geotechnical investigation of the bedrock underlying the Sydney Tar Ponds. Information gathered from the drilling will help determine the design and construction of the sheet pile wall of the clear channel which will be built to allow two fresh-water brooks to pass through the Tar Ponds without becoming contaminated. Bart Longyear did the work under contract to Maritime Testing.
It’s taken more than 100 years to create the toxic stew of the Tar Ponds in Sydney, N.S. The federal and Nova Scotia governments hope to have it cleaned up in 10, at a cost of $400 million.
The Tar Ponds, the marshy estuary of Muggah Creek near where it flows into Sydney Harbour, contain the heaviest concentration of contaminants on the 250-acre site of the former steel mill that, in the early years of the 20th century, produced close to half Canada’s steel. The mill closed in 2001.
Considerable work has been done elsewhere on the site in recent years — smoke stacks and derelict buildings have been removed, an engineered containment system has transformed a former municipal dump into a grass-covered hill, a new primary sewage treatment plant has diverted millions of litres of raw sewage from Muggah Creek and a barrier has been built across the mouth of Muggah Creek to prevent contaminants from flowing into Sydney Harbour during the cleanup which is coming up. This year marks the start of work on the ponds themselves
SYDNEY TAR PONDS AGENCY
Construction of a barrier across the mouth of Muggah Creek where it flows into Sydney Harbour began in June 2006 and was completed in September 2006. The barrier will prevent contaminants from the Tar Ponds from escaping into the harbour during the cleanup process in the ponds.
Contaminants in the 77 acres of the Tar Ponds include about 700,000 tonnes of contaminated sediment, mainly heavy metals and polycyclic aromatic hydrocarbons (PAHs) — both byproducts of coke production — as well as about 3.8 tonnes of polychlorinated biphenyls (PCBs) that were dumped there over the years.
After a number of costly false starts dating back to the early 1980s, the federal and provincial governments agreed that the best solution to clear up the site would be a combination of stabilization and solidification.
Stabilization makes the contaminants less mobile, less soluable and less toxic while solidification mixes cement and other hardening agents with the sludge to harden it and contain the contaminants.
While the federal and provincial governments are confident the solution will work, environmentalists have expressed misgivings about what they view as an unproven technology.
An environmental review panel also had some questions about the process and there will be considerably more pilot testing than planned to make sure the system works.
By mid-May, Earth Tech and CBCL Ltd. are scheduled to present their completed plan for carrying out the cleanup. While working on the plan, they have been drawing up tender documents for work to go out for tender later this year.
Among this year’s projects are creating new channels for Coke Ovens Brook and Muggah Creek as they pass through the Tar Ponds; construction of a new decontamination facility, originally planned to be open but now planned to be contained in a steel building; and building a second-generation landfill, a lined site that has facilities to deal with water infiltration and landfill gases.
The first step for the rechannelization projects will be installation of sheet piling. The project is still awaiting environmental approvals to begin excavation but the piling does not require environmental approval, said John Chesal, communications officer with the Sydney Tar Ponds Agency.
Plans for the landfill were also affected by regulations.
“We had planned to use the CFB landfill site,” Chesal said, “but the provincial regulations changed Jan. 1 and we were required to build a second-generation landfill.”
Among the materials destined for the landfill are a number of creosote-treated timbers used as cribbing for the cooling pond for the mill.
Chesal said the agency has made significant efforts to keep contracts to a size that local contractors can handle. One of the largest was the $7-million realignment of Coke Ovens Brook, elsewhere on the site, carried out by Riverside Developments Ltd., and the construction of the barrier at the mouth of Muggah Creek carried out by J. & T. Van Zutphen Bros. Construction. Both projects were on-time and under budget.
Chesal said the work started this year is expected to be complete in this construction season.
The work on the contaminants in the rest of the ponds — the largest part of the cleanup — will get under way next year.
| MOST POPULAR STORIES |
- Mobile-crane accident puts pedestrian in hospital
- Bank of Canada’s interest-rate “hawks” begin to ascend
- Liberal “Green Shift” plan fails to address transit woes, industry officials say
- Crane lands at Ledcor’s Shangri-La site
- Enhance Energy plans to build commercial carbon-dioxide pipeline
- 20 Most Popular Stories
| CURRENT STORIES |
- WorkSafeBC blames Canada Line crane death on lack of operator training
- Plan to certify B.C. crane operators continues
- Chinese construction market offers opportunities and risks to Canadian contractors
- Construction boom helps portable restroom businesses “clean up”
- TransCanada Corp. begins construction plans for $320-million Kibby wind-power project
- Saskatchewan’s skilled trades workers head home
| ALEX’S BLOG |

Reed Construction Data Chief Economist Alex Carrick discusses current developments in Canada's economic environment. He also shares light-hearted reflections on life and current events.
Economics Blog More 
- More on China and Japan – Similarities and Differences (July 24, 2008)
- A Higher Proportion of Homeownership, Mortgages and Condos (July 23, 2008)
- Intentions to Renovate and Buy a Home Both Decline in 2008 (July 22, 2008)
Lifestyle Blog More 
- Doing the Economics Tango (July 21, 2008)
- Taking Somebody Else’s Child to the Cottage (July 14, 2008)
| PROJECT NEWS BRIEFS |
Updates on Canadian construction projects from Reed Construction Data’s research team. More 
- BMW Canada celebrates groundbreaking at site of new corporate headquarters (Jul 23, 2008)
- Thompson Rivers University receives funding for library, First Nations learning centre (Jul 21, 2008)
- Vrancor negotiates with City of Oshawa for downtown brownfield site (Jul 21, 2008)
- Hilton Hotels plans Waldorf-Astoria hotel on Sherbrooke Street (Jul 21, 2008)
- Manitoba Hydro plans new Riel Converter Station (Jul 21, 2008)