Building around planes, trains, ferries and automobiles can be a logistical nightmare
David Powley, owner of Power Steel, said the job of building a pedestrian walkway over railway tracks in Whistler, home of the 2010 Winter Olympics, ranked in the top three in degree of difficulty, up there with building toll booths at BC Ferries’ Tsawwassen terminal and the Pier “C” domestic terminal at Vancouver International Airport.
Power Steel won the $450,000 contract to ship a 60-ton steel bridge from the Greater Vancouver area to Whistler and to erect the walkway while CN Rail trains came around a bend twice a day.
Power Steel & Erectors Inc.
The walkway was transported 120 kilometers in three sections. Two cranes had to be used for the two-day hoist over the railway tracks.
The up-scale Nita Lake Lodge, initially scheduled to open last year and now set to begin operation in late August, built a railroad station near its 75-suite, 14-condo facility and called for tenders to build a walkway to connect the station with a nearby hiking trail.
Powley said the two-a-day train interruption was handled with cooperation from CN Rail, which assigned employee Chub Lovie to coordinate with Power Steel crews and supplied two flag persons.
Power Steel & Erectors Inc.
Building a pedestrian walkway over railway tracks in Whistler ranked in the top three in degree of difficulty
The walkway was transported 120 kilometers (75 miles) in three sections by Ludman’s Trucking and crews had to move road dividers at Lion’s Bay to accommodate the wide loads. For the tricky section over the railway tracks, Powley said two Eagle West cranes had to be used for the two-day hoist.
He said the other two challenging jobs had different sets of problems. At Tsawwassen, Powley had to deal with rusting screens required by BC Ferries while at YVR (Vancouver International Airport), terminal access and asbestos were the headaches.
| MOST POPULAR STORIES |
- Mobile-crane accident puts pedestrian in hospital
- Bank of Canada’s interest-rate “hawks” begin to ascend
- Liberal “Green Shift” plan fails to address transit woes, industry officials say
- Crane lands at Ledcor’s Shangri-La site
- Enhance Energy plans to build commercial carbon-dioxide pipeline
- 20 Most Popular Stories
| CURRENT STORIES |
- WorkSafeBC blames Canada Line crane death on lack of operator training
- Plan to certify B.C. crane operators continues
- Chinese construction market offers opportunities and risks to Canadian contractors
- Construction boom helps portable restroom businesses “clean up”
- TransCanada Corp. begins construction plans for $320-million Kibby wind-power project
- Saskatchewan’s skilled trades workers head home
| ALEX’S BLOG |

Reed Construction Data Chief Economist Alex Carrick discusses current developments in Canada's economic environment. He also shares light-hearted reflections on life and current events.
Economics Blog More 
- More on China and Japan – Similarities and Differences (July 24, 2008)
- A Higher Proportion of Homeownership, Mortgages and Condos (July 23, 2008)
- Intentions to Renovate and Buy a Home Both Decline in 2008 (July 22, 2008)
Lifestyle Blog More 
- Doing the Economics Tango (July 21, 2008)
- Taking Somebody Else’s Child to the Cottage (July 14, 2008)
| PROJECT NEWS BRIEFS |
Updates on Canadian construction projects from Reed Construction Data’s research team. More 
- BMW Canada celebrates groundbreaking at site of new corporate headquarters (Jul 23, 2008)
- Thompson Rivers University receives funding for library, First Nations learning centre (Jul 21, 2008)
- Vrancor negotiates with City of Oshawa for downtown brownfield site (Jul 21, 2008)
- Hilton Hotels plans Waldorf-Astoria hotel on Sherbrooke Street (Jul 21, 2008)
- Manitoba Hydro plans new Riel Converter Station (Jul 21, 2008)