February 4, 2008
CITY OF PRINCE GEORGE
River Road in Prince George has been raised to help prevent the town from flooding. Raising the road to act like a dike was one method the municipality employed to ease the flood risk.
Emergency Response
Roads used in effort to stop river from flooding
City of Prince George turns to roadbuilders to help stop ice-jammed Nechako river from overflowing
The construction of a temporary raised roadway has been completed along the Nechako River, as part of the main flood prevention system for the city of Prince George.
The ice began to jam up in the Nechako River after several days of low temperatures at about -20 degrees in early December.
Chunks of the ice jam dislodged, flowing downstream and stacked more than three metres high.
The highest flood levels ever recorded in Prince George were discovered when rising temperatures melted the ice and it overflowed the river banks.
A local state of emergency was declared on Dec. 11, when the ice jam caused the flooding and evacuation of homes and businesses north of the river in the Pulp Mill Road area.
A major ice shift and water surge on Jan. 5 resulted in significant new flooding on Pulp Mill Road and on the south side of the Nechako River along River Road.
A new build up of ice forced water to overflow the Gabion dike system in lower level areas.
In response to the second round of flooding, the construction of a temporary raised roadway by city engineers and contractors began on Jan. 10.
The road provides access to local businesses and functions as the main flood defense system for Prince George.
“We are just finishing some off ramps to a forest products plant. For all intents and purposes that project is complete,” said Kevin Brown, liaison officer for the city of Prince George.
“The temporary raised roadway is the main safety mechanism for downtown Prince George and the CN railway.”
The temporary new raised road was built on River Road and acts as temporary diking.
The road is eight metres high and was raised to .6 metres above the 200 year flood level. The majority of the construction was completed by Jan. 15.
“That piece of raised roadway is the second section constructed along that stretch of River Road. The first section was done several weeks ago, in response to the first bit of flooding on Dec 11,” Brown said.
Flood mitigation work played a critical role in reducing the damage from the second flood on Jan. 5.
When water levels dropped from the first round of flooding in late December, the city began construction activities associated with flood mitigation.
This work included the construction of the portable gabion diking and earth berms, removal and hauling of debris, pumping of flooded areas, engineering consulting and security.
“Experts say the uncertainty with the ice jam could continue into April and May. We just don’t know. So, we are preparing for the worst and hoping to reduce the impact of the ice jam as much as possible,” Brown said.
“We could face further shifts and water surges, which is the reason we are raising River Road. This will protect us in the event of another significant flood event.”
The city of Prince George is built on a flood plain area, which includes a business and industrial area, downtown and residential developments.
The industrial area on River Road has three saw mills, four forest processing plants, warehousing, trucking, petroleum distribution and the CN Yard.
The railway runs from the port of Prince Rupert and passes through Prince George on the way to Edmonton.
This is an important transportation route, because it links the growing container port in Prince Rupert with the U.S. market.
The City of Prince George is working on a plan that would see $4.2 million dollars worth of improvements to River Road.
The plan would include a $2.3 million water main extension and a third section of improvements along the CN line on the east side of the intermodal yard.
The city hopes to receive funding for the project from the Asia – Pacific Gateway programs, since River Road is an integral part of the intermodal operations of CN.
The total cost of the city’s response and recovery program for the ice jam and flood was pegged at more than $3.5 million on Jan 25.
The majority of these costs will be covered by the PEP.
| MOST POPULAR STORIES |
- Trucking industry hit hard by British Columbia’s new carbon tax
- ATCO wins contract to build massive worker village in United Arab Emirates
- Aecon Group wins contract to twin Highway 21 near Edmonton
- Royal Architectural Institute of Canada launches wiki on carbon-neutral building
- Bank of Canada’s interest-rate “hawks” begin to ascend
- 20 Most Popular Stories
| CURRENT STORIES |
- Crane lands at Ledcor’s Shangri-La site
- Enhance Energy plans to build commercial carbon-dioxide pipeline
- Detailed designs underway for Circle Drive bridge over South Saskatchewan River
- Federal government launches Wage Earner Protection Program
- Bosa Construction builds high-rise Claremont condo in Westwood Village
- Supreme Court sides with owners in three construction contract disputes
- Liberal “Green Shift” plan fails to address transit woes, industry officials say
- Mobile-crane accident puts pedestrian in hospital
- Master Builders Queensland calls for Australian safety blitz after scaffolding deaths
| ALEX’S BLOG |

Reed Construction Data Chief Economist Alex Carrick discusses current developments in Canada's economic environment. He also shares light-hearted reflections on life and current events.
Economics Blog More 
- Some Other Keys to Commodity Pricing (2) (July 18, 2008)
- Some Other Keys to Commodity Pricing (1) (July 17, 2008)
- There are Exciting Answers to the World’s Food Shortage (July 16, 2008)
Lifestyle Blog More 
- Taking Somebody Else’s Child to the Cottage (July 14, 2008)
- Which Letter of the Alphabet is the Funniest? (July 7, 2008)
| PROJECT NEWS BRIEFS |
Updates on Canadian construction projects from Reed Construction Data’s research team. More 
- George Brown College wins $61.5 million in provincial funds for Toronto Waterfront campus (Jul 14, 2008)
- Plans get underway for Saline Creek Plateau and Parsons Creek communities (Jul 14, 2008)
- Life Construction seeks trade prices for 500 on Sherbourne condominium project (Jul 14, 2008)
- Working designs nearly complete for Joseph and Wolf Lebovic Jewish Community Campus (Jul 11, 2008)
- Alberta commits $200 million to Federal Building renovation and redevelopment (Jul 10, 2008)
