February 4, 2008
Roadbuilding
Cariboo Connector program proceeding at cautious pace
Work on the Cariboo Connector, a $2 billion program announced in 2005 aimed at twinning Highway 97 from Cache Creek to Prince George, is not going fast enough for some northern communities.
After more than two years, only about 10 kilometres have been twinned on the 460-km route.
“At that rate, it will take 40 years,” said Quesnel Mayor Nate Bello, adding that the province is not even calling it a project but a program.
His community has seen few results in Phase 1 where the program identifies highway areas needing upgrades based upon urban congestion and safety.
An estimated $200 million will be spent over five years twinning these areas.
“We had one project that was about three kilometres a couple of years ago, but it was delayed. We hope they will go ahead because they have bought the property,” Bello said.
Cache Creek Mayor John Ranta said there was more talk about the route during the last Liberal election than action today.
The Cache Creek portion includes twinning Highway 97 to Highway 99, the cut-off for Lillooet and the Whistler area.
“The government has expressed an inclination for having the four lanes done by the 2010 Olympics, but for that to happen they better get to work,” he said, adding that part of the delay hinges upon twinning the highway through First Nations lands.
Rosalind Thorn, executive director of the B.C. Construction Association North, said her members will be pressing government to get more tenders out this year after a lull that hit after the Simon Fraser Bridge’s plans were cancelled after coming in over budget.
“It is now a design-bid-build contract and that is happening now,” she said.
Surespan Construction received a $31.6 million contract to build the four-lane bridge in November 2007.
The project cost is $42 million (engineering and highway approaches) with completion in 2009 and the federal government contributing $18 million. Pile driving has currently started.
“We will be pressing government to continue and carry on with the phases of the project all the way to Cache Creek,” Thorn said.
The Connector will link two thirds of the northern province with the rest of B.C. as well as provide access to the regional hospital, a new cancer clinic slated for 2010 and the university.
It will also bring economic benefits to the northern city linking the oil and gas, mining and forestry centres as well as gaining quicker access to major consumers of raw materials such as China.
Bill Rose, Ministry of Transport program manager for the Cariboo Connector, has heard the concerns.
“Some of our stakeholders had hoped projects would be rolled out faster,” he said, but added that much of the delay has hinged upon obtaining engineering designs, negotiations with the federal government to determine where federal funding might be forthcoming, and budget constraints.
Rose said that projects won’t go ahead until his department has fully explored funding options from the federal government, which should take another two or three months.
Only three projects have been completed on the twinning of the 460-km highway corridor.
They are: Plett Road (a $3.5 million contract to Integrated Contractors Ltd. of Prince George, finished in 2006); Fletchers (a $2.8 million contract going to Peter’s Bros. Construction Ltd. of Penticton and finished in 2005). As well, a small improvement in Williams Lake is finished.
Currently only one project – the Simon Fraser Bridge – is under construction.
The ministry is hoping to put out to tender three new projects in 2008 with construction starting this year.
The projects to tender include the Prince George south weigh scale relocation and four-laning, Dale Lake road to Dragon Lake where the road will be twinned over a two-km area and Wright Station curves, near Lac La Hache for safety reasons.
Many projects in Phase 1 still need to be completed.
Cache Creek Mayor Ranta said he is eager to see construction start, not only because of the Olympics, but because traffic going through his area has rebounded to levels prior to the opening of the Coquihalla Highway.
He has discussed with other communities the federal government’s on-going work to twin sections of the Trans Canada. Cache Creek, lies at the junction for much of the east-west and north-south traffic on the highway.
“With the amount of traffic we are seeing,” he said.
“It’s long over-due.”
| MOST POPULAR STORIES |
- International Living Building Institute launches new challenge
- Government takes over Northwest Territories P3 bridge project
- Dominion Construction gets two B.C. contracts
- Infrastructure gets funding increase in B.C. Budget 2010
- Society aiming for net zero energy for all new builds by 2030
- 20 Most Popular Stories
| TODAY’S TOP CONSTRUCTION PROJECTS |
These projects have been selected from 316 projects with a total value of $3,217,267,405 that Reed Construction Data Building Reports reported on yesterday.
$391,000,000 Burnaby BC Tenders
$37,000,000 Wembley AB Prebid
$32,700,000 Vancouver BC Tenders
| CURRENT STORIES |
- Government takes over Northwest Territories P3 bridge project
- Canadian construction experts visit earthquake-ravaged Haiti
- Winnipeg gets new water treatment plant
- Weighing in on the Tercon Contractors appeal decision
- Construction restarting on hospital in Fort St. John, British Columbia
- In new movie, Hamilton construction worker becomes ‘Defendor’ at night
- ‘Quality product cannot come from cutting corners on safety’
- Shop owner suing VANOC over pre-Olympics road construction disruptions
- St. Marys Cement plant workers go on strike in Bowmanville, Ontario
- Province holding information sessions on new Ontario accessibility standard
- Work continues on Market Wharf condo in Toronto
- Chilliwack Cultural Centre project sets tilt-up concrete record
- Pursuit of LEED could result in professional negligence, insurance executive warns
- U.S. construction unemployment could get even worse
- SNC-Lavalin subsidiary Profac under scrutiny over federal contract billing
- As prices surge, China may raise interest rates
- Canadian soldiers repair blown-up bridge in Afghanistan
- Canadian Mechanical Contracting Education Foundation offering Gold Seal course for supervisors
- Slovak construction minister sacked amid corruption scandal
| ALEX’S ECONOMICS BLOG |

Reed Construction Data Chief Economist Alex Carrick discusses current developments in the North American economic environment with emphasis on the construction industry.
- A dozen incredible measurement sets on Canada’s changing ethnic mix (March 9, 2010)
- How fragile is recovery around the world? (March 3, 2010)
- The world financial crisis goes into extra innings (February 25, 2010)
- More

| PROJECT NEWS BRIEFS |
Updates on Canadian construction projects from Reed Construction Data’s research team. More 
- Rounthwaite Dick & Hadley Architects begin work on arena plans for Flamborough, Ontario (Aug 17, 2009)
- Orillia Market Square aims for LEED Silver certification (Jun 25, 2009)
- Designs for new York Region District School Board building features energy efficiency (Jun 23, 2009)
- IPC Energy considers Milford location for future wind farm (May 22, 2009)
- Waterloo partnership seeks LEED Silver for West Side Family YMCA and District Library (May 22, 2009)