February 4, 2008
SNC-LAVELIN
Port Coquitlam’s Coast Meridian Overpass, scheduled for completion in early 2010, will bring increased traffic flow to a city bisected by CPR rail yards. However, building the bridge while work continues in the yards poses significant engineering and construction challenges.
Infrastructure
Port Coquitlam overpass overcomes challenges
A new overpass in Port Coquitlam will address long standing traffic issues, but not without significant engineering and construction challenges.
Port Coquitlam has long been physically separated between north and south by Canadian Pacific train tracks and yards spanning the entire city, resulting in bottlenecked traffic and bisected communities.
The City of Port Coquitlam decided in 2000 that some form of large-scale bridge was needed to alleviate traffic problems, but many challenges lay ahead before work could begin on the Coast Meridian Overpass, a new, four-lane overpass budgeted at $132 million.
After years of negotiations with both CPR and TransLink, construction of the overpass is set to begin this month.
“The city is basically bisected by the CPR yards, with few passes over or under. All we have is the Mary Hill Bypass and the Shaughnessy Underpass,” said Igor Zahynacz, Port Coquitlam director of engineering and operations.
The CMO will link north and south Port Coquitlam with two lanes of traffic in each direction, sidewalks, bicycle lanes and transit facilities, in the process reducing congestion on Lougheed Highway, but getting the bridge built in the first place carried many challenges, Zahynacz said.
“It’s a very limited location. We’re working on the CPR yard, but we can’t affect operations in any way, so it’s quite a difficult project. It’s a very limited location, and it’s difficult to bring trucks in. It’s actually easier to build a bridge over water,” he said.
Among the restrictions bid-winning firm SNC-Lavelin will have to work around is CPR’s insistence that no intermediate supports can be used to keep the bridge in place.
“The bridge has to built, and then launched across. The solution to the lack of intermediate supports is to use a cable-stay design as part of the launch,” Zahynacz said.
He estimated construction of the bridge will take about two years, with completion scheduled for early 2010.
The project is also part of Port Coquitlam’s official community plan, which aims to make the city more supportive of transit and environmentally sustainable.
Despite a serious labour crunch in British Columbia’s construction industry, Zahynacz said that he does not foresee any problems in obtaining the skilled labour necessary to complete the project.
“It’s a design-build project, essentially a bid for submission, so labour costs are all factored in ahead of time,” he said.
SNC-Lavelin’s contract is for $94.5 million, with Translink contributing $60 million to the $132 million budget.
The rest of the funding comes from the City of Port Coquitlam’s development charges and other sources of revenue, Zahynacz said.
SNC-Lavelin’s previous projects include work on the $1.9 billion Canada Line and the William R. Bennett Bridge across Okanagan Lake.
| MOST POPULAR STORIES |
- Massive blaze destroys Quattro 2 condo still under construction
- U.S.-style housing crisis possible in Canada, Merrill Lynch Canada report finds
- Bantrel Construction employee dies in accident at Petro-Canada refinery
- Battle brews over green-rating systems for high-rise residential buildings
- Winnipeg Centre MP decries use of foreign trades on portions of airport expansion project
- 20 Most Popular Stories
| CURRENT STORIES |
- Bombardier Transportation will showcase streetcars at Vancouver 2010 Winter Games
- British Columbia government provides bridge workers with emergency funds
- Reco Decoration Group pays $26,000 in damages after BSA finds illegal software
- Correction
- BC Hydro meets with VRCA members to present $5.3-billion expansion plan
- Supermétal Structures lands $6-million steel-supply contract for two Saskatchewan projects
- Peter Kiewit Sons Co. wins $392-million contract for six run-of-river hydroelectric projects
- ATCO Water will design, build and operate water, wastewater infrastructure projects
- Concrete helps lead the way to green, sustainable construction, Willmer says
- Two Ontario workers injured on Garden City Skyway bridge
- Prefabricated steel-stud panels cut construction time for Solterra Developments
- Canadians join massive Angola infrastructure renewal project
- Next Hibernia oil platform will employ concrete gravity base structure (CFBS) technology
- RMCAO launches first North American ‘Eco Certified Concrete Facility’ program
- Kelowna’s Bennett Bridge project expands SCC use
- Pontoon controversy hinders bridge decommissioning
- Special Delivery
- Concrete soil solidification and stabilization technology helps reclaim industrial sites
- Solar asphalt energy technology heats up
- Seven Construction Safety Network member companies receive BCRMCA safety awards
- Inland Aggregates starts up state-of-the-art facility
- New ENX scale weighs in as Alberta’s largest
- Whitemud Resources opens plant to produce metakaolin concrete additive
- National concrete conference takes place December 3-4, 2008
| ALEX’S BLOG |

Reed Construction Data Chief Economist Alex Carrick discusses current developments in Canada's economic environment. He also shares light-hearted reflections on life and current events.
Economics Blog More 
- Why are the Conservatives and Stephen Harper taking it on the Chin? (October 10, 2008)
- Standing up in a Convertible while Driving under a Bridge (October 9, 2008)
- Phrase of the Day: Libor (October 8, 2008)
Lifestyle Blog More 
- Three Cities with a Lot in Common: Calgary, Edmonton and Venice (September 29, 2008)
- How to Get Ahead in this Life (September 25, 2008)
| PROJECT NEWS BRIEFS |
Updates on Canadian construction projects from Reed Construction Data’s research team. More 
- Viljoen Architects readies working drawings for Stonebridge by the Bay (Sep 15, 2008)
- REC Silicon plans $1.2-billion manufacturing plant in Quebec (Sep 15, 2008)
- Construction underway at Interfor’s Adams Lake sawmill (Sep 11, 2008)
- Alcan moves closer to construction of Kitimat aluminum smelter (Sep 11, 2008)
- Town of Oliver presses on with plans for wine village (Sep 11, 2008)