Understanding payment provisions in CCDC 2
This is the final instalment in our series of articles on the 2008 CCDC 2.
In this article we highlight some further important changes in the CCDC 2, of which to be aware.
First, portions of the payment provisions in GC 5 have been altered to extend the times for review by the Consultant and payment by the Owner.
In the 1994 CCDC 2, payment was to be made within five days of the certification of the progress draw by the Consultant with certification being required within 10 days of the Consultant receiving the application.
Now, an application for payment is to be reviewed within 10 calendar days of receipt by the Consultant and payment by the Owner is to take place within 20 days after receipt by the Consultant of the application for payment, or the last day of the monthly payment period, for which the application for payment was made.
A similar change has been made with respect to applications for substantial performance.
This is where the timeline for the Consultant to respond to an application for substantial performance has been extended to 20 days from the combined 17 days, which existed in the 1994 version.
Second, the insurance provisions of the 2008 CCDC 2 have been extensively modified.
Limits for general liability insurance have been increased to $5 million from $2 million with the deductible rising to $5,000 from $2,500.
In addition, the wording in the 2008 CCDC 2 is clearer with respect to the Contractor’s obligation to ensure that both the Owner and the Consultant are covered for the negligence of the Contractor.
Interestingly, the 2008 CCDC 2 specifically incorporates the latest version of the CCDC 41 Insurance Requirements in effect at the time of bid closing.
CCDC 41 is expected to evolve more readily with insurance trends regarding limits and exclusions than the standard form contract.
Accordingly, it will be important for Contractors and Owners alike to keep a current version of CCDC 41 on hand.
Third, the indemnity provisions have been amended so that the indemnity obligations as between the Owner and the Contractor mirror one another.
Significantly, while there continues to be limits on the indemnity to be provided as between the Owner and the Contractor, there is explicitly no limit on indemnification for claims made by third parties.
Fourth, there is an entirely new condition, which deals with the issue of mould and sets out a process by which the costs arising from the discovery of mould, whether toxic or not, are to be dealt with by the Contractor and Owner.
This includes the costs of obtaining independent expert advice as to the existence and/or cause of mould on site.
Finally, the warranty period of one year has remained unchanged.
However, there is a new provision, which clarifies that extended warranties to be issued by warrantors are to be issued in the name of the Owner and that a Contractor’s responsibility with respect to extended warranties only extends to obtaining the warranty.
Many of the changes to the CCDC 2 are in the nature of clarifications of existing contractual provisions where clearly the authors were attempting to make the contract easier to understand.
However, as discussed in our series of articles, there are also substantive changes to this widely used standard form contract with which industry players need to be familiar.
Norm Streu and Chris Hirst are lawyers in the Construction & Engineering Group in the law firm of Alexander Holburn Beaudin & Lang LLP. Norm is a Past Chair of the Vancouver Regional Construction Association. If you have any questions about this article, or any construction law related issue, please feel free to call Norm or Chris at (604) 484-1700.
| MOST POPULAR STORIES |
- Trucking industry hit hard by British Columbia’s new carbon tax
- ATCO wins contract to build massive worker village in United Arab Emirates
- Aecon Group wins contract to twin Highway 21 near Edmonton
- Royal Architectural Institute of Canada launches wiki on carbon-neutral building
- Bank of Canada’s interest-rate “hawks” begin to ascend
- 20 Most Popular Stories
| CURRENT STORIES |
- Crane lands at Ledcor’s Shangri-La site
- Enhance Energy plans to build commercial carbon-dioxide pipeline
- Detailed designs underway for Circle Drive bridge over South Saskatchewan River
- Federal government launches Wage Earner Protection Program
- Bosa Construction builds high-rise Claremont condo in Westwood Village
- Supreme Court sides with owners in three construction contract disputes
- Liberal “Green Shift” plan fails to address transit woes, industry officials say
- Mobile-crane accident puts pedestrian in hospital
- Master Builders Queensland calls for Australian safety blitz after scaffolding deaths
| ALEX’S BLOG |

Reed Construction Data Chief Economist Alex Carrick discusses current developments in Canada's economic environment. He also shares light-hearted reflections on life and current events.
Economics Blog More 
- Some Other Keys to Commodity Pricing (2) (July 18, 2008)
- Some Other Keys to Commodity Pricing (1) (July 17, 2008)
- There are Exciting Answers to the World’s Food Shortage (July 16, 2008)
Lifestyle Blog More 
- Taking Somebody Else’s Child to the Cottage (July 14, 2008)
- Which Letter of the Alphabet is the Funniest? (July 7, 2008)
| PROJECT NEWS BRIEFS |
Updates on Canadian construction projects from Reed Construction Data’s research team. More 
- George Brown College wins $61.5 million in provincial funds for Toronto Waterfront campus (Jul 14, 2008)
- Plans get underway for Saline Creek Plateau and Parsons Creek communities (Jul 14, 2008)
- Life Construction seeks trade prices for 500 on Sherbourne condominium project (Jul 14, 2008)
- Working designs nearly complete for Joseph and Wolf Lebovic Jewish Community Campus (Jul 11, 2008)
- Alberta commits $200 million to Federal Building renovation and redevelopment (Jul 10, 2008)