LATEST NEWS
Roadbuilding | Engineering | Water & Wastewater | Concrete | Steel | Trade Contracting | Skills Training
July 28, 2008
A tunnel boring machine, similar to the one pictured above, remains trapped under Langstaff Road after 1,000 cubic metres of soil collapsed on it during construction of a portion of the York-Durham Sewer System project.
Preparations begin for removal of buried Ontario boring machine
McNally Construction and Aecon Group, working as a joint venture, have begun preparations to remove the $5-million tunnel boring machine that has been trapped underground.
A five-by-30-metre secant pile wall shaft is being built to help remove the buried 100-tonne tunnel boring machine (TBM) and its assorted trailing equipment to allow completion of the project in the York region north of Toronto.
The 60-metre train created by the TBM and its trailing equipment of backup pumps and electrical equipment is trapped under approximately 1,000 cubic metres of soil.
“Work commenced on a recovery shaft in late June, and will be ongoing until spring 2009,” explained Laura McNally, of McNally Construction.
“In order to minimize impacts on the project schedule, another TBM will be launched (in August) from the shaft at the east end of the tunnel drive (Bathurst Street, south of Highway 407).
“The TBM will mine west and be removed at the recovery shaft, and the two sections of tunnel will be connected at the shaft.”
McNally/Aecon has tackled three sewer expansion projects in York Region. Main pieces in the group’s underground project arsenal were Earth Pressure Balance TBMs designed by Lovat.
The TBMs used by McNally/Aecon are 3.3 metres in diameter and erect a precast concrete segment liner system that is 1.21 metres in length with a 2.74 metre inner diameter and 3.12 metre external diameter.
Two months ago, six workers operating a TBM 22 metres under Langstaff Road were progressing through “the most challenging ground conditions on the projects,” a very fine sand and silt with water pressure of 1.5 bar (21.7 psi), explained McNally.
“A breach of the tail seals occurred approximately 150 metres west of the intermediate shaft,” she McNally.
“This resulted in an inflow of material, which the crew was not able to control. The tunnel was safely evacuated and secured [and] no one was injured.”
About 1,000 cubic metres of material entered the tunnel over a 48-hour period, causing a large sinkhole on the surface and damage to a local watermain. McNally/Aecon is still investigating how exactly the breach occurred.
Soil conditions for the second TBM bore are different, consisting of sand and till for the majority of the drive.
However, mitigation measures are being reviewed for when fine silt and fine sand are encountered closer to the recovery shaft.
“Recovery of the tunnel is paramount to completion of the project. The TBM will be removed during this tunnel repair process,” said McNally.
Dealing with sensitive ground to bore through was an issue in completing the 4.1 kilometre tunnel project under 19th Avenue.
“This project involved some highly sensitive environmental features, including tunnelling through the Oak Ridges Moraine,” noted McNally.
“Diligence in all operations, combined with good cooperation with the owner’s consultant (Earth Tech Canada), resulted in completion of the project with no environmental impacts.”
The ground conditions on the 19th Avenue project varied between till and sand with water pressure up to 1.8 bar (26.1 psi).
Several watercourses, which are fish spawning grounds and form the upper tributaries of the Rouge River, were challenges to contend with. Also, the presence of Redside Dace, a species of minnow which is threatened provincially and endangered nationally, required close attention. The five-kilometre Bathurst Trunk Sewer tunnel from Steeles Avenue to Autumn Hill Boulevard (north of Hwy 407) primarily consisted of clay, till and sand, with water pressure up to 1 bar (14.5 psi).
Completion of the trunk sewer is expected sometime in November. Any silts encountered here and on the 19th Avenue project have been “coarser grained” than those on the Langstaff project, noted McNally.
| MOST POPULAR STORIES |
- International Living Building Institute launches new challenge
- Infrastructure gets funding increase in B.C. Budget 2010
- Society aiming for net zero energy for all new builds by 2030
- Terrane Metals Corp. set to start construction on mine near Fort St. James, British Columbia
- Dominion Construction gets two B.C. contracts
- 20 Most Popular Stories
| TODAY’S TOP CONSTRUCTION PROJECTS |
These projects have been selected from 342 projects with a total value of $2,911,425,288 that Reed Construction Data Building Reports reported on yesterday.
HOTEL RESORT, GOLF COURSE & WELLNESS CENTRE
$477,000,000 Kelowna BC Prebid
$229,795,000 Edmonton AB Negotiated
$50,000,000 Winnipeg MB Prebid
| CURRENT STORIES |
- Government takes over Northwest Territories P3 bridge project
- Canadian construction experts visit earthquake-ravaged Haiti
- Winnipeg gets new water treatment plant
- Weighing in on the Tercon Contractors appeal decision
- Construction restarting on hospital in Fort St. John, British Columbia
- In new movie, Hamilton construction worker becomes ‘Defendor’ at night
- ‘Quality product cannot come from cutting corners on safety’
- Shop owner suing VANOC over pre-Olympics road construction disruptions
- Fraud charges laid against former head of Quebec labour union
- Pursuit of LEED could result in professional negligence, insurance executive warns
- Province holding information sessions on new Ontario accessibility standard
- Work continues on Market Wharf condo in Toronto
- Chilliwack Cultural Centre project sets tilt-up concrete record
- WSIB report a clear response to ideas we submitted, Ontario General Contractors Association chief says
- SNC-Lavalin subsidiary Profac under scrutiny over federal contract billing
- As prices surge, China may raise interest rates
- Canadian soldiers repair blown-up bridge in Afghanistan
- Canadian Mechanical Contracting Education Foundation offering Gold Seal course for supervisors
- Slovak construction minister sacked amid corruption scandal
- Historic Kingston Dry Dock restored, enhanced
- Centre for Energy Innovation in Windsor, Ontario built using Termobuild HVAC system
- Canadian Standards Association parking garage standard gets tougher
- Accelerated schedules a challenge for vinyl flooring
- Good materials, shoddy workmanship produces poorly performing floor
| ALEX’S ECONOMICS BLOG |

Reed Construction Data Chief Economist Alex Carrick discusses current developments in the North American economic environment with emphasis on the construction industry.
- A dozen incredible measurement sets on Canada’s changing ethnic mix (March 9, 2010)
- How fragile is recovery around the world? (March 3, 2010)
- The world financial crisis goes into extra innings (February 25, 2010)
- More

| PROJECT NEWS BRIEFS |
Updates on Canadian construction projects from Reed Construction Data’s research team. More 
- Rounthwaite Dick & Hadley Architects begin work on arena plans for Flamborough, Ontario (Aug 17, 2009)
- Orillia Market Square aims for LEED Silver certification (Jun 25, 2009)
- Designs for new York Region District School Board building features energy efficiency (Jun 23, 2009)
- IPC Energy considers Milford location for future wind farm (May 22, 2009)
- Waterloo partnership seeks LEED Silver for West Side Family YMCA and District Library (May 22, 2009)



