LATEST NEWS
Roadbuilding | Engineering | Water & Wastewater | Concrete | Steel | Trade Contracting | Skills Training
July 28, 2008
A tunnel boring machine, similar to the one pictured above, remains trapped under Langstaff Road after 1,000 cubic metres of soil collapsed on it during construction of a portion of the York-Durham Sewer System project.
Preparations begin for removal of buried Ontario boring machine
McNally Construction and Aecon Group, working as a joint venture, have begun preparations to remove the $5-million tunnel boring machine that has been trapped underground.
A five-by-30-metre secant pile wall shaft is being built to help remove the buried 100-tonne tunnel boring machine (TBM) and its assorted trailing equipment to allow completion of the project in the York region north of Toronto.
The 60-metre train created by the TBM and its trailing equipment of backup pumps and electrical equipment is trapped under approximately 1,000 cubic metres of soil.
“Work commenced on a recovery shaft in late June, and will be ongoing until spring 2009,” explained Laura McNally, of McNally Construction.
“In order to minimize impacts on the project schedule, another TBM will be launched (in August) from the shaft at the east end of the tunnel drive (Bathurst Street, south of Highway 407).
“The TBM will mine west and be removed at the recovery shaft, and the two sections of tunnel will be connected at the shaft.”
McNally/Aecon has tackled three sewer expansion projects in York Region. Main pieces in the group’s underground project arsenal were Earth Pressure Balance TBMs designed by Lovat.
The TBMs used by McNally/Aecon are 3.3 metres in diameter and erect a precast concrete segment liner system that is 1.21 metres in length with a 2.74 metre inner diameter and 3.12 metre external diameter.
Two months ago, six workers operating a TBM 22 metres under Langstaff Road were progressing through “the most challenging ground conditions on the projects,” a very fine sand and silt with water pressure of 1.5 bar (21.7 psi), explained McNally.
“A breach of the tail seals occurred approximately 150 metres west of the intermediate shaft,” she McNally.
“This resulted in an inflow of material, which the crew was not able to control. The tunnel was safely evacuated and secured [and] no one was injured.”
About 1,000 cubic metres of material entered the tunnel over a 48-hour period, causing a large sinkhole on the surface and damage to a local watermain. McNally/Aecon is still investigating how exactly the breach occurred.
Soil conditions for the second TBM bore are different, consisting of sand and till for the majority of the drive.
However, mitigation measures are being reviewed for when fine silt and fine sand are encountered closer to the recovery shaft.
“Recovery of the tunnel is paramount to completion of the project. The TBM will be removed during this tunnel repair process,” said McNally.
Dealing with sensitive ground to bore through was an issue in completing the 4.1 kilometre tunnel project under 19th Avenue.
“This project involved some highly sensitive environmental features, including tunnelling through the Oak Ridges Moraine,” noted McNally.
“Diligence in all operations, combined with good cooperation with the owner’s consultant (Earth Tech Canada), resulted in completion of the project with no environmental impacts.”
The ground conditions on the 19th Avenue project varied between till and sand with water pressure up to 1.8 bar (26.1 psi).
Several watercourses, which are fish spawning grounds and form the upper tributaries of the Rouge River, were challenges to contend with. Also, the presence of Redside Dace, a species of minnow which is threatened provincially and endangered nationally, required close attention. The five-kilometre Bathurst Trunk Sewer tunnel from Steeles Avenue to Autumn Hill Boulevard (north of Hwy 407) primarily consisted of clay, till and sand, with water pressure up to 1 bar (14.5 psi).
Completion of the trunk sewer is expected sometime in November. Any silts encountered here and on the 19th Avenue project have been “coarser grained” than those on the Langstaff project, noted McNally.
| MOST POPULAR STORIES |
- Alberta construction labour outlook not so bright
- How to get security clearance for federal contracts
- Canadian temporary foreign workers bill still has a low profile
- $10 million steel dragon makes a grand entrance in Chilliwack, British Columbia
- Calgary construction projects posted online
- 20 Most Popular Stories
| TODAY’S TOP CONSTRUCTION PROJECTS |
These projects have been selected from 315 projects with a total value of $1,397,361,898 that Reed Construction Data Building Reports reported on yesterday.
$169,000,000 Calgary AB Negotiated
$50,000,000 Province of Alberta AB Prebid
$31,400,000 Chilliwack BC Tenders
| CURRENT STORIES |
- Union highlights deficiencies in construction of Vancouver 2010 Olympic village
- Engineers advocate Qualifications Based Selection for public construction projects
- Construction restarts at stalled oilsands project in Fort McMurray, Alberta
- Competition produces new visions of seniors’ housing
- Worker fatally crushed in Edmonton
- Wolfe Island, Ontario wind farm in operation
- Decision to delay Darlington nuclear power plant carries job cost
- Boutique building takes shape in Toronto
- Algonquin College’s new Ottawa facility will have trades working together
- Project phasing keeps Sault Ste. Marie, Ontario industry near full employment
- Solaris @ Metrogate Phases I and II shaping up in Toronto
- Stantec to rehabilitate major Boston sewer tunnel
- U.S. non-residential construction rises as general industry spending drops
- Developers order Vancouver 2010 Olympic village review
- Romanian Bishop calls office building ‘hideous’ and ‘illegal’
- U.S. manufacturing in ‘slow recovery’ mode
- PTI Group lands field accommodation job for 2010 Vancouver Olympics
- Malaysia bans high-rises on resort island
- Deere’s salaried workers in U.S. line up for buyout program
| ALEX’S ECONOMICS BLOG |

Reed Construction Data Chief Economist Alex Carrick discusses current developments in the North American economic environment with emphasis on the construction industry.
| PROJECT NEWS BRIEFS |
Updates on Canadian construction projects from Reed Construction Data’s research team. More 
- Orillia Market Square aims for LEED Silver certification (Jun 25, 2009)
- Designs for new York Region District School Board building features energy efficiency (Jun 23, 2009)
- Vancouver Convention Centre expansion sets new standards for environmental design (May 22, 2009)
- Waterloo partnership seeks LEED Silver for West Side Family YMCA and District Library (May 22, 2009)
- IPC Energy considers Milford location for future wind farm (May 22, 2009)