March 16, 2009
The 70,000 kilogram truss can be seen during installation. It is keeping a heritage building several metres off the ground in downtown Vancouver.
Innovation
Vancouver building suspended after financing falls through
Downtown Vancouver has become home to one of the more unique construction sites in the country.
Since November 2007, one of the city’s heritage buildings has been suspended six storeys in the air.
In November financing fell through for the $180-million Jameson House condo/office development, however construction had already begun.
A 21-metre deep hole had been dug at the site on West Hastings for the 37-storey tower’s foundation and parking garage.
To keep the nearly 90 year old Ceperley Rounsfell building from falling into the hole, it was enveloped in a steel truss and that’s where it remains.
The measure was intended to be temporary, however, as the company continues to try and secure new financing for the project, the building continues to hover several metres above the street.
The truss weighs 70,000 kilograms, measures 40 metres long, eight metres high and nine metres wide and cost about $2.5 million to construct and erect, said Bruce Simmonds, an engineer with LNS Services, the company that built the truss and worked on other aspects of the project.
“Our scope was to demolish the existing buildings, support the heritage buildings, and excavate and shore for the new building and parking garage,” he said.
Pacific Blasting Division carried out the demolition, LNS Services Division supplied and installed the truss, and Bel Pacific Division did the excavation and shoring.
The assembly and erection of the truss took about 10 workers eight weeks to complete, while the excavation took another six months.
The Jolly Taxpayer Pub had been demolished, creating a vacant lot next to the site, which was used as a staging area.
Before installation of the truss could begin, about 20 concrete filled caissons measuring one metre in diameter by 20 meters long were drilled into the sidewalk on Hastings and the back lane to support the truss.
The truss was fabricated locally by Kay-Son Steel Fabricators Ltd. in Coquitlam and trucked in pieces to the site and assembled on the ground in the staging area.
Once assembled, Simmonds said, the truss, which is made up of steel sections with bolted connections, was lifted into position above the heritage building using two cranes.
“The building basement concrete floor was removed and slots excavated to accept heavy steel needle beams under the building foundations at six locations across the width of the building,” he said.
Twelve Steel hangers were connected from the truss to the needle beams on both sides of the building.
Hydraulic jacks were attached to each hanger.
The system was then energized, he said, and the weight of the 1,200 tonne building was taken by the truss.
“The hydraulic jacking system is self leveling, such that each jack will take its appropriate amount of weight to ensure the building remains level,” Simmonds explained.
This allowed excavation below the building to begin.
While having the building resting on the truss was supposed to be a temporary measure, Simmonds said the structure could last for several decades.
“The truss was designed for seismic loads and should last 25 to 30 years or more,” he said.
Once the parking garage is built up to the underside of the building, and the truss and needle beams are removed, the roof of the parking garage will become the new basement floor for the heritage building.
The Ceperley Rounsfell building has Heritage A status, which is the City of Vancouver’s highest rating.
The facade of another heritage building, nearby on Hastings Street, was also partially rebuilt as part of the project.
Construction, however, remains on hold and the Ceperley Rounsfell building remains suspended in mid-air.
“This is a unique design,” Simmonds said. “I don’t know of anything similar to this in North America.”
The Ceperley Rounsfell building, was built in 1921 by Vancouver pioneer Henry Ceperley. It was being restored as part of the Jameson House condo/office development.
The aim of the project, which was designed to achieve LEED gold certification, is to restore and integrate two heritage buildings to create a mixed-use building with retail and restaurants on the bottom three floors, eight floors of office space and 25 floors of condominiums.
| MOST POPULAR STORIES |
- Government takes over Northwest Territories P3 bridge project
- Dominion Construction gets two B.C. contracts
- Venues decommissioned in Olympic afterglow
- Construction restarting on hospital in Fort St. John, British Columbia
- International Living Building Institute launches new challenge
- 20 Most Popular Stories
| TODAY’S TOP CONSTRUCTION PROJECTS |
These projects have been selected from 313 projects with a total value of $3,164,198,755 that Reed Construction Data Building Reports reported on yesterday.
$250,000,000 Division No 4 MB Prebid
$149,200,000 Fort Nelson BC Tenders
HYDROELECTRIC GENERATING STATIONS
$68,000,000 Sunshine Coast RD BC Negotiated
| CURRENT STORIES |
- Venues decommissioned in Olympic afterglow
- Canadian Construction Association chair bids farewell
- Wood being considered as preferred building material for federal projects
- Grizzly Oil Sands seeks approval for project near Fort McMurray
- Search continues for sustainable architecture
- Seven British Columbia communities sign Wood First agreements
- U.S. construction employment declines in January
- Ottawa unveils plan to cut red tape
- Pride, sadness as Hogg's Hollow memorial unveiled
- Commemorative quilt gets permanent home
- Despite safety improvements, underground dangers still exist
- ‘Sandhogs’ who perished had diverse personal stories
- Commemorative quilt also a story of victims’ families
- Filling labour gap a top priority for incoming Canadian Construction Association chair
- Niagara Construction Association president worked her way up
- Pursuit of LEED could result in professional negligence, insurance executive warns
- Nova Scotia officials ‘comfortable’ covering cost of $60-million wind plant
- New Brunswick plans to install wildlife fencing for highway construction season
| ALEX’S ECONOMICS BLOG |

Reed Construction Data Chief Economist Alex Carrick discusses current developments in the North American economic environment with emphasis on the construction industry.
- Sub-sector investment spending intentions from Statistics Canada’s latest survey (March 17, 2010)
- A dozen incredible measurement sets on Canada’s changing ethnic mix (March 9, 2010)
- How fragile is recovery around the world? (March 3, 2010)
- More

| PROJECT NEWS BRIEFS |
Updates on Canadian construction projects from Reed Construction Data’s research team. More 
- Rounthwaite Dick & Hadley Architects begin work on arena plans for Flamborough, Ontario (Aug 17, 2009)
- Orillia Market Square aims for LEED Silver certification (Jun 25, 2009)
- Designs for new York Region District School Board building features energy efficiency (Jun 23, 2009)
- IPC Energy considers Milford location for future wind farm (May 22, 2009)
- Waterloo partnership seeks LEED Silver for West Side Family YMCA and District Library (May 22, 2009)



