LATEST NEWS
Concrete | Trade Contracting | Engineering | Heavy Equipment | Green Building | Building Envelope | Water & Wastewater
May 11, 2009
RICHARD GILBERT
The new Best Western motel in Kamloops, B.C. is being constructed using precast concrete panels.
Key Construction employs Advance Precast system at Kamloops motel project
The newest motel in Kamloops, B.C. is being built using a unique precast concrete system, instead of traditional wood frame construction techniques.
Key Construction is the main contractor in charge of the construction of the new Best Western Mountainview in Kamloops.
The 53,500 sq. ft. motel will have 95 rooms.
“All the panels we use are pre-cast before construction, but things are put together with what could be called a Lego Block system,” said Frans Van der Woning, owner of Key Construction. “It is a reasonable cost and much safer compared to a traditional wood frame building.”
The pre-cast concrete panels were manufactured by Kelowna-based Advance Precast Ltd.
“A project of this ilk is determined by its longevity and value down the road,” said Wayne Rains, general manager of Advance. “This building will cost a little more initially compared to wood frame construction, but this building has a structure that doesn’t deteriorate and will appreciate in value over time. In 50 years, the building will be virtually as good or better.”
The sandwich precast panels have a styrofoam core or a thermal break.
They are used in motels, hotels and residential buildings, where cold areas are unacceptable for customer requirements. The panels have limited sections of solid concrete and are produced in a CSA Certified Precast Concrete Plant.
Van der Woning worked closely with an architect to design a building that takes full advantage of the precast concrete system.
According to Rains, the design represents a further development in terms of detail and functionality, when compared to another hotel he did recently for this owner in Clearbrook.
“The wall panels come with all the necessary boxes and conduit already cast, as well as the necessary holes for plumbing, piping, sprinklers, water lines and drainage,” he said.
“The door frames and window openings are already cast in the walls, which need to be touched up, but are ready for painting. This is an all non-combustible building. Sprinklers were not required, but in this case we put them in anyway.”
Van der Woning also worked closely with the architect to include several green features in the building.
“We set out to make a green building as far as possible,” he said.
“We use geothermal heating and cooling, as well as energy efficient lighting. The electrical system has been designed for low use of energy.”
Another benefit of the precast design is that maintenance of the building is much easier than traditional wood frame construction.
As part of the design, piping has been contained in horizontal and vertical fire rated shafts, which make it accessible after construction is completed.
Van der Woning said one of the main benefits of using a precast concrete system is that once the design is completed and the structure is on paper, the parts can be manufactured.
This means the projects time line can be compressed, because work on the building can begin before work begins on the construction site.
The first phase of construction was to put down the structural foundation, which consists of frost walls, footings and a floor.
Due to soil conditions in the area, eight feet of structural fill was needed to support the foundation.
The precast sections were then transported by truck from Kelowna and stored on the site until they were needed.
The assembly of the sections only requires four men inside the building and a crane operator.
“Once the preparation is done and you start construction, the building can be put up very quickly, which could be financially beneficial to the owner,” explained Van der Woning.
In this case, the owner was not in rush, so construction began in December and is scheduled for completion in August.
Consultants on the project include ITEC Systems Design Ltd. (mechanical); NAK Engineering Ltd. (electrical); Ross Book Engineering (structural); and AMEC (geotechnical).
| MOST POPULAR STORIES |
- International Living Building Institute launches new challenge
- Government takes over Northwest Territories P3 bridge project
- Dominion Construction gets two B.C. contracts
- Independent contractors association criticizes Burnaby’s fair wage policy
- Infrastructure gets funding increase in B.C. Budget 2010
- 20 Most Popular Stories
| TODAY’S TOP CONSTRUCTION PROJECTS |
These projects have been selected from 316 projects with a total value of $201,737,936,657 that Reed Construction Data Building Reports reported on yesterday.
NATURAL GAS PLANT, POWER PLANT
$200,000,000,000 Capital RD BC Prebid
$200,000,000 Vancouver BC Prebid
CONDOMINIUM APARTMENT, HOTEL, COMMERCIAL TOWER
$160,000,000 Vancouver BC Negotiated
| CURRENT STORIES |
- Government takes over Northwest Territories P3 bridge project
- Canadian construction experts visit earthquake-ravaged Haiti
- Winnipeg gets new water treatment plant
- Weighing in on the Tercon Contractors appeal decision
- Construction restarting on hospital in Fort St. John, British Columbia
- In new movie, Hamilton construction worker becomes ‘Defendor’ at night
- ‘Quality product cannot come from cutting corners on safety’
- Shop owner suing VANOC over pre-Olympics road construction disruptions
- Canadian Construction Association chair bids farewell
- Excavation underway for St. Gabriel Manor condos in Toronto
- Pursuit of LEED could result in professional negligence, insurance executive warns
- St. Marys Cement plant workers go on strike in Bowmanville, Ontario
- Construction continues on the Nautilus at Waterview condo project in Etobicoke, Ontario
- Search continues for sustainable architecture
- U.S. construction unemployment could get even worse
- WorkSafeBC issued record number of fines in 2009
- Canada job numbers up in February
- BC Hydro awards purchase agreements for 19 clean wind, run-of-river energy projects
- Concern over presence of hermit beetles delays Poland road job
- Russian official calls 2014 Winter Olympics protests “unconstructive”
- Construction moving forward on Ho Chi Minh City tunnel
| ALEX’S ECONOMICS BLOG |

Reed Construction Data Chief Economist Alex Carrick discusses current developments in the North American economic environment with emphasis on the construction industry.
- A dozen incredible measurement sets on Canada’s changing ethnic mix (March 9, 2010)
- How fragile is recovery around the world? (March 3, 2010)
- The world financial crisis goes into extra innings (February 25, 2010)
- More

| PROJECT NEWS BRIEFS |
Updates on Canadian construction projects from Reed Construction Data’s research team. More 
- Rounthwaite Dick & Hadley Architects begin work on arena plans for Flamborough, Ontario (Aug 17, 2009)
- Orillia Market Square aims for LEED Silver certification (Jun 25, 2009)
- Designs for new York Region District School Board building features energy efficiency (Jun 23, 2009)
- IPC Energy considers Milford location for future wind farm (May 22, 2009)
- Waterloo partnership seeks LEED Silver for West Side Family YMCA and District Library (May 22, 2009)



