LATEST NEWS
Concrete | Steel | Heavy Equipment | Engineering | Building Envelope | Trade Contracting
May 11, 2009
COLLAVINO CONSTRUCTION GROUP
50,000 cubic yards of concrete was slated to be poured just to get the Freedom Tower job up to street level.
Collavino Construction Group’s crew puts in overtime on Freedom Tower
Renzo Collavino is far from home, deep in a 16-acre hole at what was and what will be one of New York’s most famous landmarks.
Work at the World Trade Center Freedom Tower is progressing slowly; too slowly, in fact, dragged back by a series of issues around how to best preserve existing structures and the subterranean rail lines below the massive hole excavated after the towers were downed in the infamous 911 attacks.
“The project is several months behind schedule,” said Collavino, who with brother Paolo and father Mario, make up Collavino Construction Group, the Windsor-based outfit which is the main sub-contractor on the US$300 million-plus concrete job.
Add in the credit crisis and the sudden evaporation of money needed to keep construction projects like the Freedom Tower rolling and it’s been a rough few months.
Renzo and his key managers live in New York and commute home to Ontario every two weeks.
Despite the chaos and the pressure of the ever-ticking clock, his voice is calm and contained.
These are delays outside of his realm of control.
His focus remains on the below-grade portions of the work, with special attention on the elevator shafts and ensuring there’s no thermal cracking.
“We’re on double shifts seven days a week now so we are doing our part to be back on schedule by summer,” he said.
The US$3 billion Freedom Tower will have an illuminated spire and top out at 1,776 feet — an auspicious number marking the birth of the American republic.
It will feature an observation deck at 1,300 feet with a square glass parapet paying homage to the original Twin Towers.
The tower rises from a cubic foundation and tapers into triangles while forming an octagon at its centre.
Over the 105 floors will be 2.6 million square feet of space which are slated to open in 2013.
The concreting operations are still below grade, with about 50,000 cubic yards total pour slated to get the job to street level.
Then, the structural steel will commence followed by pouring of concrete on metal decks, concrete elevator core walls and auxiliary works such as walkways, slabs, stairs, pads and curbs.
It sounds easy enough but the logistics are a nightmare. The lower Manhattan site is smack dab in the middle of a historic area with narrow streets and limited access.
Materials can only move by schedule, early in the morning or at night, and nothing can sit on the street waiting for a delivery window for more than 30 minutes.
Still, getting a workforce hasn’t been an issue as it might be on other jobs.
“Everyone wants to work on this, to make a contribution,” he said. “There’s a lot of pride surrounding the construction of this tower.”
Indeed, for many of the trades, their fathers, uncles and cousins worked on the original structures and creating a new structure has become a mission and a statement.
The job is also technically challenging.
“We’re dealing with 16,000 psi concrete on the elevator shafts where there’s a 160F temperature requirement and the maximum allowable variation from the inner and outer walls is 30F,” he said. “So we’re using ice during the initial curing process in both summer and winter to control the temperature.”
The elevator shaft walls vary from two to six feet and have a considerable amount of reinforcing steel.
“I’ve never seen anything like it,” he said.
The design has been predicated on the events that transpired on Sept 11, 2001, to ensure that the building will never suffer the same tragic fate as its predecessor, the Twin Towers.
The original World Trade Center tower collapsed when heat from burning jet fuel weakened the steel structural components, leading to failure and a domino effect. This time, designers and engineers are trying to ensure it will never happen again.
All the rebar is bent and laid by hand, he said, adding local union rules prevent the use of pre-bent rebar delivered to site.
The project is approaching grade with expected completion in mid to late summer.
“In the next coming months we will be focusing our attention on organizing and planning the above grade works, which will include a four foot thick, 70 foot high blast wall around the perimeter of the base of the tower, Collavino stated.
“Though this project has its daily challenges, we continue to move forward towards the completion of the tower, a symbol of freedom and a testament that America still stands strong.”
| MOST POPULAR STORIES |
- Government takes over Northwest Territories P3 bridge project
- Dominion Construction gets two B.C. contracts
- Venues decommissioned in Olympic afterglow
- Construction restarting on hospital in Fort St. John, British Columbia
- International Living Building Institute launches new challenge
- 20 Most Popular Stories
| TODAY’S TOP CONSTRUCTION PROJECTS |
These projects have been selected from 313 projects with a total value of $3,164,198,755 that Reed Construction Data Building Reports reported on yesterday.
$250,000,000 Division No 4 MB Prebid
$149,200,000 Fort Nelson BC Tenders
HYDROELECTRIC GENERATING STATIONS
$68,000,000 Sunshine Coast RD BC Negotiated
| CURRENT STORIES |
- Venues decommissioned in Olympic afterglow
- Canadian Construction Association chair bids farewell
- Wood being considered as preferred building material for federal projects
- Grizzly Oil Sands seeks approval for project near Fort McMurray
- Search continues for sustainable architecture
- Seven British Columbia communities sign Wood First agreements
- U.S. construction employment declines in January
- Ottawa unveils plan to cut red tape
- Pride, sadness as Hogg's Hollow memorial unveiled
- Commemorative quilt gets permanent home
- Despite safety improvements, underground dangers still exist
- ‘Sandhogs’ who perished had diverse personal stories
- Commemorative quilt also a story of victims’ families
- Filling labour gap a top priority for incoming Canadian Construction Association chair
- Niagara Construction Association president worked her way up
- Pursuit of LEED could result in professional negligence, insurance executive warns
- Nova Scotia officials ‘comfortable’ covering cost of $60-million wind plant
- New Brunswick plans to install wildlife fencing for highway construction season
| ALEX’S ECONOMICS BLOG |

Reed Construction Data Chief Economist Alex Carrick discusses current developments in the North American economic environment with emphasis on the construction industry.
- Sub-sector investment spending intentions from Statistics Canada’s latest survey (March 17, 2010)
- A dozen incredible measurement sets on Canada’s changing ethnic mix (March 9, 2010)
- How fragile is recovery around the world? (March 3, 2010)
- More

| PROJECT NEWS BRIEFS |
Updates on Canadian construction projects from Reed Construction Data’s research team. More 
- Rounthwaite Dick & Hadley Architects begin work on arena plans for Flamborough, Ontario (Aug 17, 2009)
- Orillia Market Square aims for LEED Silver certification (Jun 25, 2009)
- Designs for new York Region District School Board building features energy efficiency (Jun 23, 2009)
- IPC Energy considers Milford location for future wind farm (May 22, 2009)
- Waterloo partnership seeks LEED Silver for West Side Family YMCA and District Library (May 22, 2009)



