JOC ARCHIVES

May 20, 2009

Crews go deep to repair Hamilton’s Western Sanitary Sewer Interceptor

The typical Canadian sewer line runs no deeper than about four metres below the surface. A 270-metre length of sewer line in Hamilton, Ontario lies more than 25 metres below the surface — and it needed repair.

“Everything in the system runs on gravity to achieve flow, so the line winds up that deep in order to maintain the grade,” said Kevin Bainbridge, senior project manager of Infrastructure Programming, Public Works, with Hamilton.

“The pipe was installed in 1960 as part of the Western Sanitary Sewer Interceptor using a manually-operated boring machine to dig the tunnel, and poured-in-place concrete — effectively the pipe was constructed inside the tunnel.”

The volume of concrete used in the pipe is high, with a diameter of about 1,500 mm with 375-mm thick walls.

Inspections undertaken in 1999 revealed cracking in the walls of the pipe.

“In the 1960s there wasn’t a lot of understanding of the way concrete set and we believe the cracking was the result of the curing process,” said Bainbridge.

“What came out of the inspection was our belief that there was potential for having fine ground material infiltrate through the cracks and creating cavities around the pipe that would cause structural failure of the pipe over time.”

Video inspections undertaken by PipeFlo Contracting Corp. and CRA Consultants in 2006 revealed that the cracking hadn’t gotten any worse since the original inspection.

PipeFlo and R.V. Anderson Associates Ltd. were then contracted to develop a plan of attack to see what could be done to rehabilitate the line.

“The timing of the job depends on the sewer usage at any time, so we went in at night when there’s a lot less flow and people aren’t using the toilet and the laundry and showering,” he said.

A diversion tank constructed would be used to contain the sewage flow to provide a window of operation for the contractors.

“We were willing to divert the flow to the point that we used 25 per cent of the tank’s capacity,” said Bainbridge.

Three PipeFlo crew members entered the pipe with one stationed in the shaft and two going part way into the pipe and sending inspection equipment ahead.

A surface unit maintained constant voice contact with the underground crew.

During a dry run, PipeFlo sent two different ground-penetrating radar (GPR) units about 10 metres into the pipe to determine which would be most suitable.

The diversion was a success.

“At the end of the test run, the tank was only filled to six or seven per cent of its volume,” said Bainbridge. “So we were comfortable that we had a margin of error that would allow a full 12-hour shift.”

The pipe was then examined for debris, which was to be flushed out using a special cleaning nozzle. On next entry, the GPR device was to be used to ensure that no voids existed beyond the pipe walls. A manual repair of the cracks during a 12-hour shift was the likely plan.

Print | Email | Comment

MOST POPULAR STORIES
TODAY’S TOP CONSTRUCTION PROJECTS

These projects have been selected from 342 projects with a total value of $2,911,425,288 that Reed Construction Data Building Reports reported on yesterday.

HOTEL RESORT, GOLF COURSE & WELLNESS CENTRE

$477,000,000 Kelowna BC Prebid

EDUCATIONAL BUILDING

$229,795,000 Edmonton AB Negotiated

APARTMENT BUILDING ADDN

$50,000,000 Winnipeg MB Prebid

Daily Top 10

CURRENT STORIES
ALEX’S ECONOMICS BLOG

Reed Construction Data Chief Economist Alex Carrick discusses current developments in the North American economic environment with emphasis on the construction industry.

PROJECT NEWS BRIEFS
TODAY’S TOP JOBS

More jobs 

myJobsite.ca

Your gateway to
the top careers
in construction
and design