LATEST NEWS
July 3, 2009
Oilsands Infrastructure
Construction restarts at stalled oilsands project in Fort McMurray, Alberta
The completion of a debt offering has kick started construction on a stalled oilsands project south of Fort McMurray.
“We decided back in mid January to suspend the project because oil prices collapsed and the Western World, as we knew it, looked like it was coming to an end, thanks to the bankers,” said Dick Gusella, president and CEO of Connacher Oil and Gas Ltd.
“Now the project is a go. We have raised the necessary funding. The oil price has recovered and may well be sustainable.”
Connacher is restarting construction at its Algar oilsands project after completing a debt offering worth about $200 million last month.
“We have already invested $150 million in equipment and civil work and our decision is a go on $200 million,” he said.
The $350 million total cost doesn’t include costs incurred during the suspension. It cost $14 million to bring a crane in to move and store the project.”
The new money will be used for working capital and general corporate purposes, which include funding a portion of the remaining construction, drilling and completion costs.
“I have a range of suppliers and fabricators and most of the construction work is done in a controlled shop environment by oilfield guys we have used for years,” said Gusella.
“The modules are put on skids and then onto trucks. They are welded and bolted together on site by BDR Engineering Ltd.”
Gusella said construction should begin in early July, following completion of a brief pre-start-up organizational period.
The company anticipates that construction at Algar and the drilling of 15 steam assisted gravity drainage (SAGD) well pairs will take about 275 days from the start of field activities.
This will be followed by commissioning of the plant and steaming of the SAGD well pairs, which will require an additional 120 days.
Construction of the plant and the steaming of the wells is expected to be finished by August 2010.
“We had already started building some of the long lead that were constructed in other jurisdictions,” explained Gusella. “We got an approval in November to start construction, which included land clearing, road work and drilling sites.”
The reactivation of its construction plans gives the company its second plant with a full capacity of 10,000 barrels per day of bitumen.
Connacher’s primary upstream production is from its Great Divide Pod One SAGD plant.
Construction of the second plant will replicate the process used for the first plant.
At the peak of the construction, about 260 people will be working on the site and living in Connacher’s camp.
| MOST POPULAR STORIES |
- High-tech oil sands project near Fort McMurray, Alberta could change industry
- TransCanada begins construction on British Columbia-Alberta pipeline
- VIDEO: B.C. Construction Association welcomes standardized contract forms
- Port Mann Bridge under construction
- Crane accident kills worker at construction site in Burnaby, British Columbia
- 20 Most Popular Stories
| TODAY’S TOP CONSTRUCTION PROJECTS |
These projects have been selected from 263 projects with a total value of $8,919,878,049 that Reed Construction Data Building Reports reported on yesterday.
NATURAL GAS PROCESSING FACILITY
$500,000,000 Fort Nelson BC Prebid
$250,000,000 Fort Nelson BC Negotiated
$35,000,000 Winnipeg MB Prebid
| CURRENT STORIES |
- Crane operator certification deadline looms in British Columbia
- High-tech oil sands project near Fort McMurray, Alberta could change industry
- Saskatoon bridge closed indefinitely over structural concerns
- City of Regina project turns up all sorts of surprises
- Awareness about qualifications-based selection lacking: Survey
- Canadian Institute of Steel Construction launches Steel Day
- Saskatchewan bridge collapses, causing crane to topple
- Crane tips over, killing worker and injuring two
- Saskatoon man pulled from hole at construction site
- Churchill airport gets government cash for infrastructure upgrades
- Stantec acquires health care architectural firm
- Ground broken on Halifax RCMP headquarters
- Fanshawe College’s new Centre for Applied Transportation Technologies goes green
- Vanbots continues work on York University Life Sciences Building in Toronto
- Manitoba introduces new farm building code
- Heavy rains wash away bridges to Nova Scotia fishing village
- South Korea calls for financial safety net
- Jobsite safety a shared duty: Mechanical Contractors Association
- New technology could help find Jimmy Hoffa: Study
| ALEX’S ECONOMICS BLOG |

Reed Construction Data Chief Economist Alex Carrick discusses current developments in the North American economic environment with emphasis on the construction industry.
- Canada’s construction starts in a transition phase (August 27, 2010)
- U.S. initial jobless claims rise to half a million again (August 19, 2010)
- It’s been 35 years since institutional construction starts as strong (August 6, 2010)
- More

















