LATEST NEWS
July 3, 2009
Oilsands Infrastructure
Construction restarts at stalled oilsands project in Fort McMurray, Alberta
The completion of a debt offering has kick started construction on a stalled oilsands project south of Fort McMurray.
“We decided back in mid January to suspend the project because oil prices collapsed and the Western World, as we knew it, looked like it was coming to an end, thanks to the bankers,” said Dick Gusella, president and CEO of Connacher Oil and Gas Ltd.
“Now the project is a go. We have raised the necessary funding. The oil price has recovered and may well be sustainable.”
Connacher is restarting construction at its Algar oilsands project after completing a debt offering worth about $200 million last month.
“We have already invested $150 million in equipment and civil work and our decision is a go on $200 million,” he said.
The $350 million total cost doesn’t include costs incurred during the suspension. It cost $14 million to bring a crane in to move and store the project.”
The new money will be used for working capital and general corporate purposes, which include funding a portion of the remaining construction, drilling and completion costs.
“I have a range of suppliers and fabricators and most of the construction work is done in a controlled shop environment by oilfield guys we have used for years,” said Gusella.
“The modules are put on skids and then onto trucks. They are welded and bolted together on site by BDR Engineering Ltd.”
Gusella said construction should begin in early July, following completion of a brief pre-start-up organizational period.
The company anticipates that construction at Algar and the drilling of 15 steam assisted gravity drainage (SAGD) well pairs will take about 275 days from the start of field activities.
This will be followed by commissioning of the plant and steaming of the SAGD well pairs, which will require an additional 120 days.
Construction of the plant and the steaming of the wells is expected to be finished by August 2010.
“We had already started building some of the long lead that were constructed in other jurisdictions,” explained Gusella. “We got an approval in November to start construction, which included land clearing, road work and drilling sites.”
The reactivation of its construction plans gives the company its second plant with a full capacity of 10,000 barrels per day of bitumen.
Connacher’s primary upstream production is from its Great Divide Pod One SAGD plant.
Construction of the second plant will replicate the process used for the first plant.
At the peak of the construction, about 260 people will be working on the site and living in Connacher’s camp.
| MOST POPULAR STORIES |
- Olympic construction goes down to the wire
- Two more Fort McMurray projects moving forward
- Nexen, OPTI Canada get approval for cogeneration power plant near Fort McMurray
- 5,000-room modular lodging project taking shape near Fort McMurray, Alberta
- Public-private partnerships working as intended, new report finds
- 20 Most Popular Stories
| TODAY’S TOP CONSTRUCTION PROJECTS |
These projects have been selected from 350 projects with a total value of $6,260,468,758 that Reed Construction Data Building Reports reported on yesterday.
$1,000,000,000 Peace River RD BC Prebid
$500,000,000 Saanich BC Prebid
$500,000,000 Victoria BC Prebid
| CURRENT STORIES |
- New deal allows Canadian construction firms to bid on U.S. stimulus projects
- Construction continues on Canadian Natural Resource office in St. Albert, Alberta
- Canadian Construction Association summit zeroes in on industry concerns
- Art Gallery of Alberta addition showcases steel
- 5,000-room modular lodging project taking shape near Fort McMurray, Alberta
- Five-year forecast looking up for British Columbia construction industry
- Saskatchewan gets new natural gas trades training centre
- B.C. permit numbers rise while Alberta’s fall
- Trades lack LEED understanding
- Nexen, OPTI Canada get approval for cogeneration power plant near Fort McMurray
- Aecon wins $22 million in contracts for steam generators
- SNC-Lavalin partners with Russian bank to form engineering company
- Work continues on Pearl Condos in Toronto
- ‘A good first step forward,’ Canadian construction industry says of U.S. stimulus agreement
- Government should be more flexible with stimulus project deadline, outgoing ORBA president says
- Steel provides structure for historic hotel revival in Port Hope, Ontario
- Ontario businesses scramble to ready for arrival of HST
- Construction continues on Atira Women’s Resource Society housing project in Vancouver
- Five still unaccounted for after Connecticut power plant explosion
- U.S. manufacturing employment up, but construction losses continue
- Peterborough Utilities unveils plan for 10-megawatt wind farm
- China orders local governments to pay workers on private sites
| ALEX’S ECONOMICS BLOG |

Reed Construction Data Chief Economist Alex Carrick discusses current developments in the North American economic environment with emphasis on the construction industry.
- A review of some global economic and policy expectations for 2010 (February 3, 2010)
- Synopsis of RCD’s webinar on the economic and construction outlooks (January 28, 2010)
- Increasing signs of world and U.S. economies getting back on track (January 28, 2010)
- More

| PROJECT NEWS BRIEFS |
Updates on Canadian construction projects from Reed Construction Data’s research team. More 
- Rounthwaite Dick & Hadley Architects begin work on arena plans for Flamborough, Ontario (Aug 17, 2009)
- Orillia Market Square aims for LEED Silver certification (Jun 25, 2009)
- Designs for new York Region District School Board building features energy efficiency (Jun 23, 2009)
- IPC Energy considers Milford location for future wind farm (May 22, 2009)
- Waterloo partnership seeks LEED Silver for West Side Family YMCA and District Library (May 22, 2009)



