LATEST NEWS
July 3, 2009
Oilsands Infrastructure
Construction restarts at stalled oilsands project in Fort McMurray, Alberta
The completion of a debt offering has kick started construction on a stalled oilsands project south of Fort McMurray.
“We decided back in mid January to suspend the project because oil prices collapsed and the Western World, as we knew it, looked like it was coming to an end, thanks to the bankers,” said Dick Gusella, president and CEO of Connacher Oil and Gas Ltd.
“Now the project is a go. We have raised the necessary funding. The oil price has recovered and may well be sustainable.”
Connacher is restarting construction at its Algar oilsands project after completing a debt offering worth about $200 million last month.
“We have already invested $150 million in equipment and civil work and our decision is a go on $200 million,” he said.
The $350 million total cost doesn’t include costs incurred during the suspension. It cost $14 million to bring a crane in to move and store the project.”
The new money will be used for working capital and general corporate purposes, which include funding a portion of the remaining construction, drilling and completion costs.
“I have a range of suppliers and fabricators and most of the construction work is done in a controlled shop environment by oilfield guys we have used for years,” said Gusella.
“The modules are put on skids and then onto trucks. They are welded and bolted together on site by BDR Engineering Ltd.”
Gusella said construction should begin in early July, following completion of a brief pre-start-up organizational period.
The company anticipates that construction at Algar and the drilling of 15 steam assisted gravity drainage (SAGD) well pairs will take about 275 days from the start of field activities.
This will be followed by commissioning of the plant and steaming of the SAGD well pairs, which will require an additional 120 days.
Construction of the plant and the steaming of the wells is expected to be finished by August 2010.
“We had already started building some of the long lead that were constructed in other jurisdictions,” explained Gusella. “We got an approval in November to start construction, which included land clearing, road work and drilling sites.”
The reactivation of its construction plans gives the company its second plant with a full capacity of 10,000 barrels per day of bitumen.
Connacher’s primary upstream production is from its Great Divide Pod One SAGD plant.
Construction of the second plant will replicate the process used for the first plant.
At the peak of the construction, about 260 people will be working on the site and living in Connacher’s camp.
| MOST POPULAR STORIES |
- International Living Building Institute launches new challenge
- Infrastructure gets funding increase in B.C. Budget 2010
- Society aiming for net zero energy for all new builds by 2030
- Terrane Metals Corp. set to start construction on mine near Fort St. James, British Columbia
- Budget includes $7.7 billion in infrastructure stimulus funding
- 20 Most Popular Stories
| TODAY’S TOP CONSTRUCTION PROJECTS |
These projects have been selected from 342 projects with a total value of $2,911,425,288 that Reed Construction Data Building Reports reported on yesterday.
HOTEL RESORT, GOLF COURSE & WELLNESS CENTRE
$477,000,000 Kelowna BC Prebid
$229,795,000 Edmonton AB Negotiated
$50,000,000 Winnipeg MB Prebid
| CURRENT STORIES |
- Scott Construction continues work on research centre at Vancouver General Hospital
- Independent contractors association criticizes Burnaby’s fair wage policy
- Eastern, central focus of federal budget a concern to industry
- Industry welcomes federal government’s commitment to labour-market tracking
- International Living Building Institute launches new challenge
- International snowplow championship packs ‘em in
- Study supports domed stadium for Saskatchewan Roughriders in Regina
- U.S. construction spending drops by $5.5 billion
- Canada BIM Council nears information exchange agreement with U.S. counterpart
- SNC Lavalin awarded Saskatchewan carbon capture project
- Dominion Construction gets two B.C. contracts
- Fraud charges laid against former head of Quebec labour union
- Alberta team wins silver at U.S. bricklaying championship
- New technology allows concrete to come clean
- Ontario Masonry Contractors’ Association launches design awards
- Ontario architects, general contractor associations issue joint HST bulletin
- WSIB report a clear response to ideas we submitted, Ontario General Contractors Association chief says
- McGuinty dismisses NDP land deal allegations
- Historic Kingston Dry Dock restored, enhanced
- Centre for Energy Innovation in Windsor, Ontario built using Termobuild HVAC system
- Canadian Standards Association parking garage standard gets tougher
- Accelerated schedules a challenge for vinyl flooring
- Good materials, shoddy workmanship produces poorly performing floor
| ALEX’S ECONOMICS BLOG |

Reed Construction Data Chief Economist Alex Carrick discusses current developments in the North American economic environment with emphasis on the construction industry.
- A dozen incredible measurement sets on Canada’s changing ethnic mix (March 9, 2010)
- How fragile is recovery around the world? (March 3, 2010)
- The world financial crisis goes into extra innings (February 25, 2010)
- More

| PROJECT NEWS BRIEFS |
Updates on Canadian construction projects from Reed Construction Data’s research team. More 
- Rounthwaite Dick & Hadley Architects begin work on arena plans for Flamborough, Ontario (Aug 17, 2009)
- Orillia Market Square aims for LEED Silver certification (Jun 25, 2009)
- Designs for new York Region District School Board building features energy efficiency (Jun 23, 2009)
- IPC Energy considers Milford location for future wind farm (May 22, 2009)
- Waterloo partnership seeks LEED Silver for West Side Family YMCA and District Library (May 22, 2009)



