JOC ARCHIVES

July 3, 2009

Oilsands Infrastructure

Construction restarts at stalled oilsands project in Fort McMurray, Alberta

The completion of a debt offering has kick started construction on a stalled oilsands project south of Fort McMurray.

“We decided back in mid January to suspend the project because oil prices collapsed and the Western World, as we knew it, looked like it was coming to an end, thanks to the bankers,” said Dick Gusella, president and CEO of Connacher Oil and Gas Ltd.

“Now the project is a go. We have raised the necessary funding. The oil price has recovered and may well be sustainable.”

Connacher is restarting construction at its Algar oilsands project after completing a debt offering worth about $200 million last month.

“We have already invested $150 million in equipment and civil work and our decision is a go on $200 million,” he said.

The $350 million total cost doesn’t include costs incurred during the suspension. It cost $14 million to bring a crane in to move and store the project.”

The new money will be used for working capital and general corporate purposes, which include funding a portion of the remaining construction, drilling and completion costs.

“I have a range of suppliers and fabricators and most of the construction work is done in a controlled shop environment by oilfield guys we have used for years,” said Gusella.

“The modules are put on skids and then onto trucks. They are welded and bolted together on site by BDR Engineering Ltd.”

Gusella said construction should begin in early July, following completion of a brief pre-start-up organizational period.

The company anticipates that construction at Algar and the drilling of 15 steam assisted gravity drainage (SAGD) well pairs will take about 275 days from the start of field activities.

This will be followed by commissioning of the plant and steaming of the SAGD well pairs, which will require an additional 120 days.

Construction of the plant and the steaming of the wells is expected to be finished by August 2010.

“We had already started building some of the long lead that were constructed in other jurisdictions,” explained Gusella. “We got an approval in November to start construction, which included land clearing, road work and drilling sites.”

The reactivation of its construction plans gives the company its second plant with a full capacity of 10,000 barrels per day of bitumen.

Connacher’s primary upstream production is from its Great Divide Pod One SAGD plant.

Construction of the second plant will replicate the process used for the first plant.

At the peak of the construction, about 260 people will be working on the site and living in Connacher’s camp.

Print | Email | Comment

MOST POPULAR STORIES
TODAY’S TOP CONSTRUCTION PROJECTS

These projects have been selected from 350 projects with a total value of $6,260,468,758 that Reed Construction Data Building Reports reported on yesterday.

WIND FARM

$1,000,000,000 Peace River RD BC Prebid

SEWAGE TREATMENT PLANT

$500,000,000 Saanich BC Prebid

SEWAGE TREATMENT PLANT

$500,000,000 Victoria BC Prebid

Daily Top 10

ALEX’S ECONOMICS BLOG

Reed Construction Data Chief Economist Alex Carrick discusses current developments in the North American economic environment with emphasis on the construction industry.

PROJECT NEWS BRIEFS
TODAY’S TOP JOBS

CONSTRUCTION ESTIMATOR
British Columbia-Victoria

Estimator
Ontario-Mississauga

Executive Officer
Ontario-Toronto

Communication and Events Coordinator
Ontario-Markham

Senior Estimator
Ontario-Toronto

Technical Sales
Ontario-Toronto

Quantity Surveyor/Estimator
Ontario-Oakville

PROJECT MANAGER & SITE SUPERVISOR
Ontario-Cambridge

Masonry Estimator
Ontario-Toronto

Drilling & Blasting Foreman
Ontario-Kingston

More jobs 

myJobsite.ca

Your gateway to
the top careers
in construction
and design