With the Queen Elizabeth Way shut down, six machines completed the demolition in hours.
Demolition of Ontario bridge takes hours, not days
In the brave, new world of highway bridge demolition, projects are scheduled over hours, not days. The Martindale Bridge crossing the Queen Elizabeth Way (QEW) near St. Catharines, Ont. was no exception.
“We usually set some limits and allow contractors a specific number of hours to close the highway and get the work done,” said Ministry of Transportation spokesman Will Mackenzie. “In this case, we were scheduling 10 hours for demolition because of the wideness of the bridge.”
The overpass, constructed in 1939, once supported an intra-urban streetcar line that had long since gone out of service. The additional lane, running alongside the vehicle lane, was eventually devoted strictly to pedestrian and bicycle traffic.
“Because of that feature it was a unique bridge, but it didn’t have any particular historical significance,” said Mackenzie.
“After the streetcar line was taken out, the bridge still had that part of the deck.
“Today they would use continuous welded rail, but that wasn’t the case in the 1940s. Most of that type of rail bridge used what was essentially a viaduct filled with a gravel ballast and the track sections were laid on top of that. It allowed for a smoother track and was also easier for railway maintenance.”
The bridge was demolished to be replaced by a new span as part of a $183-million upgrade contract awarded to the Dufferin Construction Company to widen the QEW.
The contract represents the last remaining section between Toronto and Niagara Falls that has not been widened to six lanes.
“There simply wasn’t enough room to widen the highway underneath the bridge,” said Mackenzie.
“Originally, the contractor came to us with a plan to detour traffic around the abutment, but later they came to us and said they could do it faster and cheaper if we could close the highway for one night.”
A new single-span four-lane underpass structure was already under construction and ready to accept traffic as the old bridge was being demolished.
“The standard procedure is to begin by laying a foot-and-a-half to two feet of gravel on the highway to protect the existing road surface underneath from falling concrete and debris,” says Mackenzie.
Tonnes of cushioning material were laid down in the initial minutes of demolition. The contractor then sent in six excavators to attack the bridge simultaneously, as concrete was hammered to rubble and hydraulic cutters sheared steel rebar.
Backup units cleared away debris as the excavators progressed. In a few hours, the road was swept clean.
“The site was cleaned up and traffic resumed along the QEW at 10:00 a.m. on Sunday as scheduled,” said Mackenzie.
| MOST POPULAR STORIES |
- Government takes over Northwest Territories P3 bridge project
- Venues decommissioned in Olympic afterglow
- Construction restarting on hospital in Fort St. John, British Columbia
- Dominion Construction gets two B.C. contracts
- Hogg’s Hollow tragedy changed Ontario’s construction industry
- 20 Most Popular Stories
| TODAY’S TOP CONSTRUCTION PROJECTS |
These projects have been selected from 371 projects with a total value of $1,380,346,147 that Reed Construction Data Building Reports reported on yesterday.
$55,000,000 Winnipeg MB CANCELLED/ DEFERRED
CONDOMINIUM APARTMENT, COMMERCIAL & HOTEL ALTS
$50,000,000 Vancouver BC Prebid
$30,000,000 Wainwright AB Prebid
| CURRENT STORIES |
- Venues decommissioned in Olympic afterglow
- Canadian Construction Association chair bids farewell
- Wood being considered as preferred building material for federal projects
- Grizzly Oil Sands seeks approval for project near Fort McMurray
- Search continues for sustainable architecture
- Seven British Columbia communities sign Wood First agreements
- U.S. construction employment declines in January
- Ottawa unveils plan to cut red tape
- Canadian Construction Association awards highlight excellence
- Pride, sadness as Hogg's Hollow memorial unveiled
- Commemorative quilt gets permanent home
- ‘Sandhogs’ who perished had diverse personal stories
- Pursuit of LEED could result in professional negligence, insurance executive warns
- New Brunswick to cover debts of troubled Atcon Group
- Ex-Quebec minister says Liberals got ‘generous’ donations from construction sector
- Regulatory delays hinder start of Mackenzie Gas Project
- Las Vegas CityCenter general contractor Perini Building suing MGM Mirage
| ALEX’S ECONOMICS BLOG |

Reed Construction Data Chief Economist Alex Carrick discusses current developments in the North American economic environment with emphasis on the construction industry.
- Sub-sector investment spending intentions from Statistics Canada’s latest survey (March 17, 2010)
- A dozen incredible measurement sets on Canada’s changing ethnic mix (March 9, 2010)
- How fragile is recovery around the world? (March 3, 2010)
- More

| PROJECT NEWS BRIEFS |
Updates on Canadian construction projects from Reed Construction Data’s research team. More 
- Rounthwaite Dick & Hadley Architects begin work on arena plans for Flamborough, Ontario (Aug 17, 2009)
- Orillia Market Square aims for LEED Silver certification (Jun 25, 2009)
- Designs for new York Region District School Board building features energy efficiency (Jun 23, 2009)
- IPC Energy considers Milford location for future wind farm (May 22, 2009)
- Waterloo partnership seeks LEED Silver for West Side Family YMCA and District Library (May 22, 2009)