CITY OF WINNIPEG
The Deacon Water Treatment Plant was originally budgeted at $205 million, but additional design features pushed that figure to $300 million.
Winnipeg gets new water treatment plant
Citizens of Winnipeg are enjoying the benefits of the Deacon Water Treatment Plant, which provides the area with top-quality clean water.
Derived from Shoal Lake in Ontario, the water is transported through a 150-kilometre aqueduct to the Deacon Reservoir, just east of the city.
The $300-million dollar project, which broke ground in the summer of 2005, employed between 275 and 400 construction workers at any given time.
The plant, the largest capital project in the city’s history, covers 12,000 square metres and can treat up to 400 million litres of water per day.
“The construction of this project wasn’t driven by any regulation,” said Tom Pearson, project director for the plant.
“The idea was conceived by the city prior to the development of the Canadian drinking water guidelines.”
The project began with a $50-million upgrade to the aqueduct, which was built during the Second World War.
“It’s constructed of unreinforced concrete because it was built when steel was at a premium,” said Pearson.
“It’s essentially a ditch with a lid on it that was designed to last 25 years. With the upgrades, we can extend the life of the aqueduct another 50 years.”
The construction contract for the water treatment plant was split up to ensure competition and to take advantage of the resources offered by many contractors instead of just one, through a period of overheated construction in the Winnipeg market.
“We needed to ensure competition,” he said.
“It’s never a good idea to put up a contract so large that only one company can bid on it.
“Also, because we were anticipating a period of active construction in the province, we were able to actually start construction on some parts of the project while we were still designing other parts.”
Builders on the project included Gateway Construction & Engineering Ltd., PCL Constructors Canada Inc., Bird Construction and Comstock Canada Ltd. with the smallest contract bid at about $10 million.
The initial budget for the plant was $205 million with a number of factors contributing to the increased cost.
“Part of it was attributable to design creep,” said Pearson.
“We didn’t originally design the plant to have standby power generation or an on-site chlorine facility. Some of the cost was the result of the overheated construction market and some of the prices of construction materials went up significantly. The unit cost for pilings doubled in a span of months and the price of concrete also increased.”
The project was initially scheduled for completion a year earlier, but local concrete contractors were so overworked, they simply couldn’t bid on the project.
“The market was very tight, so when we put the $56-million bulk concrete contract out for tender, the bidders told us that unless we adjusted the project schedule they couldn’t bid at all,” he said.
One of the biggest construction challenges involved soil stability issues, while excavating for deeper piping.
“But I think the people with the toughest job were PCL on the concrete work,” Pearson said. “There were a lot of massive pours and slabs early on in construction and then a lot of complicated formwork around the smaller tanks.”
In all, 35,000 cubic metres of concrete were poured.
Once complete, the plant went through an extensive testing regimen before it could supply water to the city.
“Just after we started the tests, the temperature of the water dropped considerably and we had a challenge dialing in the water treatment dose rates and optimizing the process,” said Pearson.
“Our water quality is quite good to begin with in terms of turbidity, but cold water is much tougher to treat than warmer water.”
| MOST POPULAR STORIES |
- Sinkhole threatens Calgary building’s stability
- Highrise tool toss lands Calgary contractor in hot water
- Mike Holmes partners with First Nations on community-building pilot project
- Pine beetle spurs infrastructure construction in British Columbia
- City of Vancouver report slams botched demolition
- 20 Most Popular Stories
| TODAY’S TOP CONSTRUCTION PROJECTS |
These projects have been selected from 372 projects with a total value of $3,335,585,749 that Reed Construction Data Building Reports reported on yesterday.
$1,200,000,000 Calgary AB Negotiated
$520,000,000 Grande Prairie AB Prebid
$75,000,000 Edmonton AB Negotiated
| CURRENT STORIES |
- Pine beetle spurs infrastructure construction in British Columbia
- Work continues on Canadian Museum of Human Rights in Winnipeg
- City of Vancouver report slams botched demolition
- Underinvestment in infrastructure costs workers and firms: report
- MMM Group oversees Calgary Airport expansion
- Underground utilities disaster looms
- Georgian College expansion goes green in Collingwood, Ontario
- Construction industry lobbies for mine development in William’s Lake, British Columbia
- Mike Holmes partners with First Nations on community-building pilot project
- PCL Constructors Canada to build new RCMP headquarters
- Construction employment edges up slightly
- Archaeological assessments an integral part of pre-construction
- Outland Camps offers flexibility from coast to coast
- VIDEO: Canada’s economy is slowing down
- City of Vancouver report slams botched demolition
- VIDEO: Canada should embrace rainscreen cladding systems
- Australian Labor government defends stimulus after allegations of political bias
- Western Construction wins contract for Bonnybrook Waste Treatment Facility
- Stimulus spending on U.S. national parks a major job creator
- Fences provide first line of defence
- Directional drilling less disruptive for locals
- Ontario Brownfield Act to change remediation rules next year
- High-tech surveillance protects construction sites from thieves
- Market grows for energy efficient construction trailers
- Site photographers focus on staying in the picture
- Fast Wrap asset protection firm coming to Canada
| ALEX’S ECONOMICS BLOG |

Reed Construction Data Chief Economist Alex Carrick discusses current developments in the North American economic environment with emphasis on the construction industry.
- Canadian railway freight traffic on a better track (July 28, 2010)
- Waiting to see if the other shoe drops in Canada (July 16, 2010)
- Who wants Canada’s oil? (July 7, 2010)
- More