SEWAGE TREATMENT PLANT ALTS Proj: 9147021-9
God's Lake 23, Division No 22 MB AWARD
God's Lake First Nation Sewage Treatment Plant, God's Lake, 547 km North of Winnipeg Tue Feb 05, 2013 14:00
4300-S531 $8,970,000 est
Start: March, 2013 Complete: February, 2014
Project:The project consists of a new sewage treatment plant, one lift station, 150 m of watermain, 115 m of waste water sewer, 240 m of forcemain and associated works. The project includes four packages that have been prepurchased, which includes a MBBR treatment unit, pre-engineered building, generator and sludge trailer.
Development:Engineering
Category:Sewage & Water plants
Owner Complete information is available to subscribers. Click HERE to find out how to subscribe.
Gen cont Complete information is available to subscribers. Click HERE to find out how to subscribe.
Project manager Complete information is available to subscribers. Click HERE to find out how to subscribe.
Civil cons eng Complete information is available to subscribers. Click HERE to find out how to subscribe.
First report Wed Nov 16, 2011. Last report Mon Feb 04, 2013.
This report Mon Mar 04, 2013.
Bid Results 
Canotech Consultants Ltd, (3769594 Manitoba Ltd), 544 Prest Ave, Winnipeg MB R2V 4R9, Phone: 204-334-0096, Fax: 204-334-0059