LIBRARY ADDN, ALTS Proj: 9086608-21
Lachine, Communauté urbaine de Montréal, comté QC START
Bibliothèque Saul-Bellow, 3100 rue St-Antoine, H8S 4B8
$9,500,000 est
Start: August, 2013 Complete: October, 2014
Note: Contract for the general contractor has been publicly tendered and awarded.
Project:cast-in-place concrete foundation, cast-in-place concrete structural frame, electric heating system, proposed environmentally friendly additions and upgrades to the existing library to increase its area to 2,621 m2. This project will be certified under the Leadership in Energy and Environmental Design (LEED) Gold Green Building Rating System.
Scope:2,621 m²; 2 storeys
Development:Addition/alterations
Category:Recreational bldgs; Public bldgs; Educational bldgs
Owner Complete information is available to subscribers. Click HERE to find out how to subscribe.
Gen cont Complete information is available to subscribers. Click HERE to find out how to subscribe.
Trade cont Complete information is available to subscribers. Click HERE to find out how to subscribe.
Project manager Complete information is available to subscribers. Click HERE to find out how to subscribe.
Coordinator Complete information is available to subscribers. Click HERE to find out how to subscribe.
Architect Complete information is available to subscribers. Click HERE to find out how to subscribe.
Landscape architect Complete information is available to subscribers. Click HERE to find out how to subscribe.
Civil cons eng Complete information is available to subscribers. Click HERE to find out how to subscribe.
Structural cons eng Complete information is available to subscribers. Click HERE to find out how to subscribe.
Mechanical cons eng Complete information is available to subscribers. Click HERE to find out how to subscribe.
Electrical cons eng Complete information is available to subscribers. Click HERE to find out how to subscribe.
Consultant Complete information is available to subscribers. Click HERE to find out how to subscribe.
Consultant Complete information is available to subscribers. Click HERE to find out how to subscribe.
Cost cons Complete information is available to subscribers. Click HERE to find out how to subscribe.
First report Mon Jul 21, 2008. Last report Fri May 17, 2013.
This report Mon Aug 26, 2013.