LIBRARY ADDN, ALTS Proj: 9086608-20
Lachine, Communauté urbaine de Montréal, comté QC NEGOTIATED/PLANS COMPLETE
Bibliothèque Saul-Bellow, 3100 rue St-Antoine, H8S 4B8
$10,400,000 est
Start: 2013 Complete: 2014
Note: Project and general contractor award following the closed tender are on hold as the amounts stated in the received proposals exceed the planned budget. Construction work start is delayed for an indetermined period.
Project:cast-in-place concrete foundation, cast-in-place concrete structural frame, electric heating system, proposed environmentally friendly additions and upgrades to the existing library to increase its area to 2,621 m2. This project will be certified under the Leadership in Energy and Environmental Design (LEED) Gold Green Building Rating System.
Scope:2,621 m²; 2 storeys
Development:Addition/alterations
Category:Recreational bldgs; Public bldgs; Educational bldgs
Owner Complete information is available to subscribers. Click HERE to find out how to subscribe.
Trade cont Complete information is available to subscribers. Click HERE to find out how to subscribe.
Project manager Complete information is available to subscribers. Click HERE to find out how to subscribe.
Coordinator Complete information is available to subscribers. Click HERE to find out how to subscribe.
Architect Complete information is available to subscribers. Click HERE to find out how to subscribe.
Landscape architect Complete information is available to subscribers. Click HERE to find out how to subscribe.
Civil cons eng Complete information is available to subscribers. Click HERE to find out how to subscribe.
Structural cons eng Complete information is available to subscribers. Click HERE to find out how to subscribe.
Mechanical cons eng Complete information is available to subscribers. Click HERE to find out how to subscribe.
Electrical cons eng Complete information is available to subscribers. Click HERE to find out how to subscribe.
Consultant Complete information is available to subscribers. Click HERE to find out how to subscribe.
Consultant Complete information is available to subscribers. Click HERE to find out how to subscribe.
Cost cons Complete information is available to subscribers. Click HERE to find out how to subscribe.
First report Mon Jul 21, 2008. Last report Fri Jan 11, 2013.
This report Fri May 17, 2013.