DRINKING WATER PRODUCTION PLANT Proj: 9168630-6
Gatineau, Communauté urbaine de l'Outaouais, comté QC PREPARING PLANS
Usine de production d'eau potable secteur Hull, , J8L 2J8
$28,600,000 est
Start: September, 2014 Complete: September, 2016
Note: Preparatory study is expected to be completed by September, 2013; preliminary plans completion and documents for pre-qualified tender is anticipated in February, 2014; detailed design completion and invited tender is scheduled for June, 2014; award and construction start is planned for September, 2014. The construction will last two years: from September, 2014, to September, 2016.
Project:cast-in-place concrete structural frame, structural steel frame, electric heating system, modernization of the drinking water production plant. The scope of the project includes upgrades and repairs to the drinking water production facilities to increase the plant production capacity.
Scope:2 storeys
Development:Engineering
Category:Sewage & Water plants
Owner Complete information is available to subscribers. Click HERE to find out how to subscribe.
Civil cons eng Complete information is available to subscribers. Click HERE to find out how to subscribe.
First report Fri Nov 09, 2012. Last report Wed Jan 30, 2013.
This report Mon Mar 04, 2013.