DEFENCE BUILDING Proj: 9106328-8
Esquimalt, Capital RD BC NEGOTIATED/START
Fleet Maintenance Facility Cape Breton - Phase V, 14 Wing, CFB Esquimalt, V9A
$92,000,000 est
Start: August, 2013 Complete: December, 2017
Note: Sub trades will be secured sequentially by tender packages. Construction will last four/five years.
Project:structural steel frame, electric heating system, construction of a fleet maintenance facility. Phase V consists of work packages 16 through 22.
Scope:100,000 square feet; 1 storey
Development:New
Category:Defence, law enforcement bldgs
Owner Complete information is available to subscribers. Click HERE to find out how to subscribe.
Const manager Complete information is available to subscribers. Click HERE to find out how to subscribe.
Const manager Complete information is available to subscribers. Click HERE to find out how to subscribe.
Architect Complete information is available to subscribers. Click HERE to find out how to subscribe.
Consultant Complete information is available to subscribers. Click HERE to find out how to subscribe.
First report Mon Aug 17, 2009. Last report Thu Dec 27, 2012.
This report Thu Jun 27, 2013.