LIGHT RAIL TRANSIT EXPANSION, STATIONS Proj: 9076095-23
Toronto, Metro Toronto Reg ON PREPARING PLANS
Eglinton Cross Town LRT, Jane St/Black Creek to Kennedy Station
$2,200,000,000 est
Start: September, 2014 Complete: 2020
Note: Owner has issued a Request for Proposal to the pre-qualified consortia to deliver the balance of the Crosstown project including the following stations: Keele LRT Station - report 9157024, Dufferin LRT - report 9157025, Bathurst Station - report 9157030, Chaplin LRT Station - report 9157034, Caledonia LRT Station - report 9157038, Eglinton West LRT station - report 9157810, Mount Pleasant LRT Station - report 9175579, Bayview LRT Station - report 9175583, Laird LRT Station - report 9175584, Avenue Road LRT Station - report 9175578, Oakwood LRT Station - report 9160768, Don Mills LRT Station - report 9175588. In addition, a related Light Rail Vehicle Maintenance & Storage Facility project can be followed under report 9160877. Further update summer 2014.
The consortia prime team members include: Crosslinx Transit Solutions: SNC-Lavalin, ACS Infrastructure Canada, EllisDon, Aecon, Dragrados Canada, IBI Group. And: Crosstown Transit Partners: Fengate Capital Management Ltd., OHL Concesiones S.A., STRABAG Inc, Bechtel Development Company Inc., Obayashi Canada Holdings Ltd.
Project:construction of a light rail line. The Crosstown will run across Eglinton Avenue between Mount Dennis (Weston Road) and Kennedy Station. The 19-kilometre corridor will include a more than 10-kilometre underground portion between Keele Street and Laird Drive. It will have 25 stations and stops, linking to bus routes, three subway stations and various GO Transit lines.
Development:New
Category:Tunnels, subways; Passenger terminals; Bridges
Owner Complete information is available to subscribers. Click HERE to find out how to subscribe.
Owner Complete information is available to subscribers. Click HERE to find out how to subscribe.
Civil cons eng Complete information is available to subscribers. Click HERE to find out how to subscribe.
Consultant Complete information is available to subscribers. Click HERE to find out how to subscribe.
First report Wed Jan 30, 2008. Last report Mon Dec 09, 2013.
This report Tue Jan 28, 2014.