MINE MILL FACILITY & UNDERGROUND MINE Proj: 9093466-6
Thompson-Nicola RD, BC DEFERRED
Harper Creek Copper-Gold-Silver Project, 25 Km from Vavenby, along the Hwy #5 Yellowhead, Clearwater, V0E
$838,095,000 est
Note: Currently completing the Feasibility Study stage and going through both the provincial and federal environmental assessment process and First Nations negotiations. The Company is on schedule to submit its formal Environmental Application shortly. Detailed engineering and construction schedules are tentative at this time. Update in early 2014.
Budget is total Capital Cost. General enquiries: info@yellowheadmining.com. Wardrop Engineering Inc are the Preliminary Economic Assessment Consultants. Laurion Consulting Inc are the Metallurgical Consultants.
Project:concrete slab on grade foundation, 02240; site preparation, 02315; excavation, 13120; industrial buildings, copper-gold-silver mine to yeild approx 3.63 billion lbs of copper, 372,000 ounces of gold & 14 million ounces of silver contained in concentrate; a mill throughput of 70,000 tonnes per day; the site to include an open pit, tailings storage facility, road & bridge upgrades, mine site facilities (offices, cafeteria, maintenace shop, 600 person staff camp, explosives storage areas etc), a new 138 kV power line/switchyard at the rail loadout facility that paralells the Yellowhead Hwy; concentrate will be loaded on B-Trains 40t capacity for hauling to the rail load-out facility in the town of Vavenby, for rail shipment to the Port of Vancouver. From there it will be shipped to smelters/refineries most likely in the Pacific Rim.
Scope:80,000 square feet; 5 structures
Development:New
Category:Processing plants; Misc industrial bldgs; Apartment bldgs
Owner Complete information is available to subscribers. Click HERE to find out how to subscribe.
Project manager Complete information is available to subscribers. Click HERE to find out how to subscribe.
Coordinator Complete information is available to subscribers. Click HERE to find out how to subscribe.
Other bldg designer Complete information is available to subscribers. Click HERE to find out how to subscribe.
Mining eng services Complete information is available to subscribers. Click HERE to find out how to subscribe.
Mining eng services Complete information is available to subscribers. Click HERE to find out how to subscribe.
Mining eng services Complete information is available to subscribers. Click HERE to find out how to subscribe.
Mining eng services Complete information is available to subscribers. Click HERE to find out how to subscribe.
Environmental cons eng Complete information is available to subscribers. Click HERE to find out how to subscribe.
Consultant Complete information is available to subscribers. Click HERE to find out how to subscribe.
Consultant Complete information is available to subscribers. Click HERE to find out how to subscribe.
Consultant Complete information is available to subscribers. Click HERE to find out how to subscribe.
Geotechnical cons Complete information is available to subscribers. Click HERE to find out how to subscribe.
Cost cons Complete information is available to subscribers. Click HERE to find out how to subscribe.
First report Tue Dec 30, 2008. Last report Tue Oct 02, 2012.
This report Mon Feb 18, 2013.