TUNNEL, PUMPHOUSES Proj: 9158412-6
L'Assomption, comté, QC CANCELLED
Tunnel Louis-Hippolyte-La Fontaine, Montréal et Longueuil
Note: Professional consultants have completed a general inspection of the Louis-Hippolyte-La Fontaine tunnel, its approaches and three pumphouses and submitted their inspection report to the owner. The owner is finalizing the scope of work and preparing documents to submit a funding request for required works to provincial authorities. The project realization may be phased. Requests for proposals (RFPs) from professional consulting firms for planning of the project phases will be issued by the owner when all approvals and funding are secured. The finalized project phases will be followed at the stage of issuance of respective RFPs. Coverage of this report has been discontinued.
Project:proposed repairs to the tunnel Louis-Hippolyte-La Fontaine (LHL), its approaches and its three pumphouses, located on Highway 25 and connecting the two St. Lawrence River shores on Montreal and Longueuil territories.
Development:Engineering
Category:Tunnels, subways; Sewage & Water plants
Owner Complete information is available to subscribers. Click HERE to find out how to subscribe.
Other cons eng serv Complete information is available to subscribers. Click HERE to find out how to subscribe.
Other cons eng serv Complete information is available to subscribers. Click HERE to find out how to subscribe.
Other cons eng serv Complete information is available to subscribers. Click HERE to find out how to subscribe.
First report Mon May 28, 2012. Last report Wed Nov 07, 2012.
This report Tue Jun 11, 2013.