HOSPITAL Proj: 9061616-36
Selkirk, Division No 13 MB CLOSED
Selkirk Regional Health Centre - Phase 2, Easton Dr & Greenwood Ave, R0E 0M0 Tue Feb 04, 2014 14:30
2013-105 $90,000,000 est
Start: June, 2014 Complete: December, 2015
Note: Owner has bid results under review. Award anticipated in 2-3 weeks.
Project:structural steel frame, electric heating system, This project consists of a 2-storey 17,370 m2 steel frame, all new, acute care health centre. The scope of work involved the supply and installation of the super structure, building envelope, interior work and all site work. The project will be certified under the Leadership in Energy and Environmental Design (LEED) Green building rating system. Phase 2 - Super structure, building envelope, interiors and general contract.
Scope:17,370 m²; 2 storeys
Development:New
Category:Hospitals
Owner Complete information is available to subscribers. Click HERE to find out how to subscribe.
Foundation cont Complete information is available to subscribers. Click HERE to find out how to subscribe.
Architect Complete information is available to subscribers. Click HERE to find out how to subscribe.
Structural cons eng Complete information is available to subscribers. Click HERE to find out how to subscribe.
Mechanical cons eng Complete information is available to subscribers. Click HERE to find out how to subscribe.
Electrical cons eng Complete information is available to subscribers. Click HERE to find out how to subscribe.
Consultant Complete information is available to subscribers. Click HERE to find out how to subscribe.
First report Thu Apr 19, 2007. Last report Wed Feb 19, 2014.
This report Tue Apr 08, 2014.