WIND FARM Proj: 9126175-10
Témiscouata, comté, QC NEGOTIATED/START
Parc éolien de la MRC de Témiscouata, St-Honoré de Témiscouata / MRC de Témiscouata / Bas-St-Laur
$65,000,000 est
Start: 2013 Complete: December, 2014
Note: General contractor has officially started works on the site. Land clearing, road and foundation construction works are underway. Sub trades are secured from an invited list.
Project:proposed construction of 23.50 MW 10-structure wind farm. The scope of the project includes installation of wind turbines, construction of electricity transmission lines, control and transformation stations. The project also includes construction of access roads.
Scope:10 structures
Development:Engineering
Category:Elect power, engineering; Misc engineering; Roads
Owner Complete information is available to subscribers. Click HERE to find out how to subscribe.
Owner Complete information is available to subscribers. Click HERE to find out how to subscribe.
Gen cont Complete information is available to subscribers. Click HERE to find out how to subscribe.
Project manager Complete information is available to subscribers. Click HERE to find out how to subscribe.
Civil cons eng Complete information is available to subscribers. Click HERE to find out how to subscribe.
First report Wed Sep 29, 2010. Last report Wed Sep 25, 2013.
This report Wed Nov 27, 2013.