ROAD, BRIDGES AND CULVERTS REHAB/REPLACEMENT Proj: 9168808-3
New Liskeard, Timiskaming Dist ON PREPARING PLANS
Hwy 65, 66, 112 & 560, various sites
$10,000,000 est
Note: Engineers to complete detailed design have been awarded. Assignment # 5012-E-0025. Schedules for tender and construction will be set based on the Ministry's internal scheduling. Further update in early 2014.
Project:rehabilitation of GWP 5105-12-00- Blanche River Bridge Site 47-020- Highway 112, 2.9km North of Hwy 11 & GWP 5242-11-00- Lost Lake Bridge (Calcite Ck) Site 47-042- Highway 560, 32km West of Jct of Hwy 65; The replacement or rehabilitation of a bridge and culverts: GWP 364-00-00- Makobe River Bridge Site 47-035- Highway 65, 0.3km East of East Jct of Hwy 65 @ Elk Lake & GWP 364-00-00- Highway 65 Rehabilitation from Highway 66, southerly 15.4km; GWP 5358-11-00- Sutton Creek Culvert Site 47-291- Highway 65, 10.9km East of North Jct of Hwy 118; GWP 5131-08-00- Crooked Creek Culvert Site 47-003- Highway 66, 8.0km West of Hwy 11; GWP 5839-05-00- Whiskey Jack Culvert Site 47-001- Highway 66, 0.3km East of Hwy 65; GWP 5242-11-00- Six Mile Creek Culvert Site 47-406- Highway 560, 9.1km West of West Jct of Hwy 65; GWP 5242-11-00- Seven Mile Creek Culvert Site 47-314- Highway 560, 10.7km West of West Jct of Hwy 65; GWP 5242-11-00- Unknown Creek Culvert Site 47-313- Highway 560, 23km West of West Jct of Hwy 65; GWP 5242-11-00- Tamarak Creek Culvert Site 47-302- Highway 560, 14.3km West of West Jct of Hwy 65; GWP 5263-10-00- Little Mollie Creek Culvert Site 47-401- Highway 560, 6.5km East of Jct of Hwy 144.
Scope:11 structures
Development:Engineering
Category:Roads; Bridges
Owner Complete information is available to subscribers. Click HERE to find out how to subscribe.
Civil cons eng Complete information is available to subscribers. Click HERE to find out how to subscribe.
First report Wed Nov 14, 2012. Last report Fri Dec 14, 2012.
This report Wed Aug 28, 2013.