| Note: | The development permit was approved and currently in working drawings. The construction schedule is unconfirmed, but likely a Spring start. Update in May/June 2013. Budget is unreleased. |
| Project: | cast-in-place concrete foundation, wood structural frame, vinyl siding exterior, wood joist roof structure, asphalt shingle roof, fuel fired heating system, 02315; excavation, 02935; landscape, 04400; exterior stone, 06220; ready-made wood trim, 09620; plastic laminate flooring, 09680; carpet, 11450; residential appliances, 09650; resilient tile flooring, heritage architectural details such as decorative brackets & multiple gables; vinyl windows; vinyl shakes; wood plank & masonry fencing; construction of a 42 unit townhouse complex with eight fourplexes, two triplexes & two duplexes; are two or three-stys; |
| Scope: | 6,132 m²; 3 storeys; 12 structures; 42 units; parking for 119 cars; 14,521 m² |
| Development: | New |
| Category: | Apartment bldgs |
| Owner | Complete information is available to subscribers. Click HERE to find out how to subscribe.
|
| Gen cont | Complete information is available to subscribers. Click HERE to find out how to subscribe.
|
| Other bldg designer | Complete information is available to subscribers. Click HERE to find out how to subscribe.
|