New guide aims to improve cost predictability for construction
Practical advice to improve construction project cost predictability is the main goal of a new guide developed by a joint federal government and industry taskforce, which included the Canadian Construction Association.
The Guide to Cost Predictability in Construction: An Analysis of Issues Affecting the Accuracy of Construction Cost Estimates looked at how to best tackle the growing problem of large discrepancies between pre-tender estimates and actual bids.
The previously agreed degree of accuracy of +/- five per cent for Class A estimates should be expanded, explained the taskforce’s chairman.
“The more we looked at it, that +/- five per cent is too narrow,” said John Westeinde, taskforce chairman, Westeinde Construction Ltd. president and CCA member.
“Even contractors bidding on the exact project with the exact circumstances, their bids varied up to 10 per cent. How can you expect a cost consultant, no matter how tuned he is on a virtual basis, to reach a better variance than that? It is not realistic.”
The taskforce developed a cost estimate variance matrix, which provides a range of estimate variance based on the level of construction documents completion in combination with an evaluation of the level of complexity of the project.
The original guiding principle of a +/- five per cent variance simply does not apply to the current construction landscape, noted Westeinde.
“Projects have become much more complex, individual and unique. For instance, there are projects in northern Canada in which weather conditions and logistics dictate costs,” he said.
“We want owners to recognize, even under the best of circumstances, it is not realistic that you should end up at +/- five per cent variance. This is not to say we should not strive for that but don’t get excited if it is at +/- five, six or seven per cent.”
The guide’s taskforce included Defence Construction Canada, Public Works and Government Services Canada, contractor, architect, engineer and costs consultant representatives.
“The report is based on their experience and a proper reflection on what is really required to do this,” said Westeinde.
“The report is directed to industry but primarily to owners and design consultants. Owners must recognize if they want to get accurate estimates beforehand, they have to have people that are qualified, but primarily, you have to allow enough time for the design consultants to complete their drawings within reasonable deadlines.”
The taskforce members found that there is no common statistical database on variances between pre-tender estimates and final bid results for Canada’s construction market.
However, the taskforce’s collective sharing of information reflected that “up to 40 per cent of tenders had low bids that varied, either up or down, by more than 30 per cent from the pre-tender estimate and fewer than 20 per cent of tenders had bids within 10 per cent of the estimate,” the guide noted. This may not be the case for all taskforce members but it agreed that cost predictability was an increasingly serious issue.
“It behooves everyone,” Westeinde said.
“From a contractor’s point of view, if there is big discrepancy, there are changes, addenda and project gets held or delayed. It is difficult for a contractor to deal with a tender that comes in way out of line.”
The taskforce delivered eight recommendations in the guide, which would help with cost predictability.
The following are highlights from those recommendations:
Utilize qualified estimating personnel throughout the life of the project for times such as budget preparation, design, tendering, post-tender review and construction phases;
Ensure all stakeholders have input early and often throughout the life of a project and that they continue to work together to identify and mitigate risk factors;
Give designers sufficient time to finalize bid documents. Provide sufficient time for estimating professionals to review 100 per cent finished documents and prepare a final Class A Estimate;
Ensure project budgets consider all essential factors and include or adjust for them when applicable. Among the essential factors to include are: the percentage variance between the project budget and potential project cost for the various classes of estimates; local influences such as shortage or abundance of skilled labour and the seasonal timing of construction;
A widely usable database for the Canadian market, that can be properly interpreted and used by the estimating industry, is required, especially for publicly funded construction that has essentially no market-force comparison. To develop and maintain a usable database one should take into consideration the current and future construction economic outlook;
Include sufficient contingency to address market volatility, timing of construction, and other exclusions in the estimate;
During tender, ensure tender-ready documents are complete and coordinated; avoid single source specifications; revise estimates during the tender period to reflect all addenda; and keep the cost consultant involved during the tender period; and
After tender, analyze bid results against estimates to maintain a lessons learned database to avoid repeating mistakes in future projects.
The guide with its complete recommendations is available as a free download at www.cca-acc.com.
| MOST POPULAR STORIES |
| TODAY’S TOP CONSTRUCTION PROJECTS |
These projects have been selected from 316 projects with a total value of $2,787,806,637 that Reed Construction Data Building Reports reported on Friday.
$1,000,000,000 Edmonton AB Prebid
$220,000,000 Medicine Hat AB Negotiated
AGRICULTURAL EXHIBITION EXPANSION
$50,000,000 Calgary AB Prebid
| CURRENT STORIES |
- Construction Site Arson
- Journal of Commerce Update for the week of May 20th, 2013
- Industry reacts to surprise B.C. Liberal majority
- Calgary Airport Tunnel
- Worker at centre of union sign up allegations speaks out
- Calgary program aims to get more people into the trades
- Midrise in the City
- Veterans battle barriers into the trades
- Government makes changes to online tendering
- SNC-Lavalin maintains that new bribery allegations have been resolved
- B.C. faces a tough battle for top talent
- Keyano College building state of the art training facility
- Essential skills can play a vital role in an apprentices' success
- Taking a closer look at the risks in green building for contractors
- Colleges conduct construction research in addition to teaching
- Skills Canada BC Competition
- Lower Mainland high school trades program is unique
- Construction Learning Forum aims to educate
- High schools looking for more industry participation
- Industrial construction supervisor program takes off
- Saskatchewan bill passed
- Edmonton garners support for regional cash for arena
- Feds pledge $5 million for Vimy memorial
- VIDEO: Competing in the trades
- Multi-employer approach needed in apprenticeships
- New Perspective
- ACEC’s input helps develop global engineering guidelines
- Clerk of works position gives peace of mind on projects
- World Trade Center developer’s plan for a 926-foot tower moving ahead
- Call for action after MOL says workers are responsible for their own safety
- Cold spring and weak construction hurt Deere’s 2013 predictions
- CanBIM reschedule June session
- More green roofs top Toronto buildings
- Witness recants testimony in Montreal corruption case
| ALEX’S ECONOMICS BLOG |

Reed Construction Data Canada’s Chief Economist Alex Carrick discusses current developments in the North American economic environment with emphasis on the construction industry.
- An Overview of Prices and Sales in the Diverging U.S. and Canadian Housing Markets (April 25, 2013)
- Canada’s Precarious Dependence on the Commodity Price Super-Cycle (April 22, 2013)
- Twenty major upcoming residential and transportation terminal construction projects - April 2013 (April 15, 2013)
- More